United States โบ Grid โบ Interconnection queues
OCTARY USA ยท INTERCONNECTION QUEUESWithdrawn queue requests in the USA (2020 requests) โ page 3
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Offshore wind project AG1-087, Sussex County Offshore wind |
440 MW | Withdrawn / abandoned |
| Offshore wind project AF2-193, Sussex County Offshore wind ยท GSOE I, LLC |
440 MW | Withdrawn / abandoned |
| Offshore wind project AF2-194, Sussex County Offshore wind ยท GSOE I, LLC |
440 MW | Withdrawn / abandoned |
| Big Horn Energy Storage Battery storage |
425 MW | Withdrawn / abandoned |
| Gas project GEN-2020-024, Sarpy County Gas |
425 MW | Withdrawn / abandoned |
| Gas project GEN-2020-035, Cass County Gas |
425 MW | Withdrawn / abandoned |
| Gibbons Creek TEERP Coal ยท TEERP Power Station LLC |
420 MW | Withdrawn / abandoned |
| Other project J1656, Vermilion County Other |
412 MW | Withdrawn / abandoned |
| Boulder Oaks Hybrid 2 Wind + storage |
411 MW | Withdrawn / abandoned |
| Solar + storage project Q343, Maricopa County Solar + storage |
410 MW | Withdrawn / abandoned |
| Bulldog Energy Storage Battery storage |
408 MW | Withdrawn / abandoned |
| Seguro Storage Battery storage |
407 MW | Withdrawn / abandoned |
| Comal Flats 1 Solar + storage |
405 MW | Withdrawn / abandoned |
| Plum Creek Solar I Solar ยท PLUM CREEK SOLAR I, LLC |
400 MW | Withdrawn / abandoned |
| Solar project 145, Williamsburg County Solar |
400 MW | Withdrawn / abandoned |
| Other project 591, Elmore County Other |
400 MW | Withdrawn / abandoned |
| Grange Solar Solar + storage |
400 MW | Withdrawn / abandoned |
| Solar + storage project 83, Pima County Solar + storage |
400 MW | Withdrawn / abandoned |
| Onshore wind project J1613, Cass County Onshore wind |
400 MW | Withdrawn / abandoned |
| Solar + storage project Q63, Pinal County Solar + storage |
400 MW | Withdrawn / abandoned |
| Other project IC-860, Baldwin County Other |
400 MW | Withdrawn / abandoned |
| Onshore wind project J1621, Mcpherson County Onshore wind |
400 MW | Withdrawn / abandoned |
| Solar project Q344 Solar |
400 MW | Withdrawn / abandoned |
| Solar + storage project IC-862, Decatur County Solar + storage |
400 MW | Withdrawn / abandoned |
| Other project IC-861, Baldwin County Other |
400 MW | Withdrawn / abandoned |
| Onshore wind project GI-2020-12, Elbert County Onshore wind |
400 MW | Withdrawn / abandoned |
| Solar project 146, Marion County Solar |
400 MW | Withdrawn / abandoned |
| Solar + storage project Q62, Pinal County Solar + storage |
400 MW | Withdrawn / abandoned |
| Solar project GEN-2020-068, Terry County Solar |
400 MW | Withdrawn / abandoned |
| Solar + storage project Q14, Pinal County Solar + storage |
400 MW | Withdrawn / abandoned |
| Solar + storage project GI-2020-13, Pueblo County Solar + storage |
374 MW | Withdrawn / abandoned |
| Gas project 149, Georgetown County Gas |
360 MW | Withdrawn / abandoned |
| Solar + storage project Company KQ, Pershing County Solar + storage |
360 MW | Withdrawn / abandoned |
| Solar project Q335, Yavapai County Solar |
360 MW | Withdrawn / abandoned |
| Gas project 150, Georgetown County Gas |
360 MW | Withdrawn / abandoned |
| Solar + storage project 1225, Juab County Solar + storage |
350 MW | Withdrawn / abandoned |
| Solar + storage project 1212, Bear Lake County Solar + storage |
350 MW | Withdrawn / abandoned |
| Solar project G0636, Morrow County Solar |
350 MW | Withdrawn / abandoned |
| Battery storage project 1217, Uinta County Battery storage |
350 MW | Withdrawn / abandoned |
| Gas project 138414, Gaston County Gas |
348 MW | Withdrawn / abandoned |
| Solar project AG1-225, Adams County Solar ยท ADAMS SOLAR PROJECT, LLC |
346 MW | Withdrawn / abandoned |
| Solar + storage project Q342, Navajo County Solar + storage |
345 MW | Withdrawn / abandoned |
| Solar + storage project AG1-543, Charles City County Solar + storage |
325 MW | Withdrawn / abandoned |
| Solar + storage project AG2-070, Charles City County Solar + storage |
325 MW | Withdrawn / abandoned |
| Gas project J1838, Dane County Gas |
320 MW | Withdrawn / abandoned |
| Luzen Solar Energy Center Solar + storage |
313 MW | Withdrawn / abandoned |
| Crossroads Storage Battery storage |
313 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2016-114, Mcpherson County Onshore wind |
310 MW | Withdrawn / abandoned |
| Anacapa Solar + storage |
309 MW | Withdrawn / abandoned |
| Solar + storage project J1756, Shelby County Solar + storage |
309 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- PJM (Mid-Atlantic, Midwest)719 ยท 47.9 GW
- CAISO (California)107 ยท 46.6 GW
- West (non-ISO utilities)184 ยท 38.3 GW
- Southeast (non-ISO utilities)178 ยท 30.1 GW
- MISO (Midcontinent)195 ยท 27.2 GW
- NYISO (New York)129 ยท 25.5 GW
- SPP (Southwest Power Pool)60 ยท 10.4 GW
- ERCOT (Texas)67 ยท 10.4 GW
- ISO-NE (New England)113 ยท 9,841 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)