United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in the USA (2020 requests) โ€” page 3

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,752246.2 GW
Active in queue117.0 GW635 requests
Agreement signed57.7 GW326 requests
Withdrawn1,752246.2 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,752 requests ยท page 3 of 36
ProjectCapacityStatusLocationRegionQueuedOnline
Offshore wind project AG1-087, Sussex County
Offshore wind
440 MWWithdrawn / abandoned Sussex, DEPJM Jul 2020target 2026
Offshore wind project AF2-193, Sussex County
Offshore wind ยท GSOE I, LLC
440 MWWithdrawn / abandoned Sussex, DEPJM Mar 2020target 2026
Offshore wind project AF2-194, Sussex County
Offshore wind ยท GSOE I, LLC
440 MWWithdrawn / abandoned Sussex, DEPJM Mar 2020target 2026
Big Horn Energy Storage
Battery storage
425 MWWithdrawn / abandoned Imperial, CACAISO Apr 2020target 2024
Gas project GEN-2020-024, Sarpy County
Gas
425 MWWithdrawn / abandoned Sarpy, NESPP Apr 20202023
Gas project GEN-2020-035, Cass County
Gas
425 MWWithdrawn / abandoned Cass, NESPP Apr 20202023
Gibbons Creek TEERP
Coal ยท TEERP Power Station LLC
420 MWWithdrawn / abandoned Grimes, TXERCOT Apr 2020target 2020
Other project J1656, Vermilion County
Other
412 MWWithdrawn / abandoned Vermilion, ILMISO Jun 2020target 2023
Boulder Oaks Hybrid 2
Wind + storage
411 MWWithdrawn / abandoned San Diego, CACAISO Apr 2020target 2023
Solar + storage project Q343, Maricopa County
Solar + storage
410 MWWithdrawn / abandoned Maricopa, AZWest Mar 2020target 2023
Bulldog Energy Storage
Battery storage
408 MWWithdrawn / abandoned Los Angeles, CACAISO Apr 2020target 2023
Seguro Storage
Battery storage
407 MWWithdrawn / abandoned San Diego, CACAISO Apr 2020target 2032
Comal Flats 1
Solar + storage
405 MWWithdrawn / abandoned Fresno, CACAISO Apr 2020target 2024
Plum Creek Solar I
Solar ยท PLUM CREEK SOLAR I, LLC
400 MWWithdrawn / abandoned Grimes, TXERCOT Jun 2020target 2023
Solar project 145, Williamsburg County
Solar
400 MWWithdrawn / abandoned Williamsburg, SCSoutheast May 2020target 2023
Other project 591, Elmore County
Other
400 MWWithdrawn / abandoned Elmore, IDWest Dec 2020
Grange Solar
Solar + storage
400 MWWithdrawn / abandoned Logan, OHPJM Apr 2020target 2023
Solar + storage project 83, Pima County
Solar + storage
400 MWWithdrawn / abandoned Pima, AZWest Sep 2020target 2023
Onshore wind project J1613, Cass County
Onshore wind
400 MWWithdrawn / abandoned Cass, NDMISO Jun 2020target 2023
Solar + storage project Q63, Pinal County
Solar + storage
400 MWWithdrawn / abandoned Pinal, AZWest Jun 2020target 2023
Other project IC-860, Baldwin County
Other
400 MWWithdrawn / abandoned Baldwin, ALSoutheast Apr 2020target 2024
Onshore wind project J1621, Mcpherson County
Onshore wind
400 MWWithdrawn / abandoned Mcpherson, SDMISO Jun 2020target 2023
Solar project Q344
Solar
400 MWWithdrawn / abandoned AZWest Mar 2020target 2021
Solar + storage project IC-862, Decatur County
Solar + storage
400 MWWithdrawn / abandoned Decatur, GASoutheast Apr 2020target 2025
Other project IC-861, Baldwin County
Other
400 MWWithdrawn / abandoned Baldwin, ALSoutheast Apr 2020target 2024
Onshore wind project GI-2020-12, Elbert County
Onshore wind
400 MWWithdrawn / abandoned Elbert, COWest Sep 2020target 2024
Solar project 146, Marion County
Solar
400 MWWithdrawn / abandoned Marion, SCSoutheast May 2020target 2023
Solar + storage project Q62, Pinal County
Solar + storage
400 MWWithdrawn / abandoned Pinal, AZWest May 2020target 2023
Solar project GEN-2020-068, Terry County
Solar
400 MWWithdrawn / abandoned Terry, TXSPP Apr 2020target 2026
Solar + storage project Q14, Pinal County
Solar + storage
400 MWWithdrawn / abandoned Pinal, AZWest Jun 2020target 2023
Solar + storage project GI-2020-13, Pueblo County
Solar + storage
374 MWWithdrawn / abandoned Pueblo, COWest Sep 2020target 2024
Gas project 149, Georgetown County
Gas
360 MWWithdrawn / abandoned Georgetown, SCSoutheast May 2020target 2024
Solar + storage project Company KQ, Pershing County
Solar + storage
360 MWWithdrawn / abandoned Pershing, NVWest Sep 2020target 2026
Solar project Q335, Yavapai County
Solar
360 MWWithdrawn / abandoned Yavapai, AZWest Mar 2020target 2023
Gas project 150, Georgetown County
Gas
360 MWWithdrawn / abandoned Georgetown, SCSoutheast May 2020target 2024
Solar + storage project 1225, Juab County
Solar + storage
350 MWWithdrawn / abandoned Juab, UTWest Apr 2020target 2023
Solar + storage project 1212, Bear Lake County
Solar + storage
350 MWWithdrawn / abandoned Bear Lake, IDWest Apr 2020target 2023
Solar project G0636, Morrow County
Solar
350 MWWithdrawn / abandoned Morrow, ORWest Jan 2020target 2023
Battery storage project 1217, Uinta County
Battery storage
350 MWWithdrawn / abandoned Uinta, WYWest Apr 2020target 2024
Gas project 138414, Gaston County
Gas
348 MWWithdrawn / abandoned Gaston, NCSoutheast Oct 2020
Solar project AG1-225, Adams County
Solar ยท ADAMS SOLAR PROJECT, LLC
346 MWWithdrawn / abandoned Adams, INPJM Sep 2020target 2023
Solar + storage project Q342, Navajo County
Solar + storage
345 MWWithdrawn / abandoned Navajo, AZWest Mar 2020target 2023
Solar + storage project AG1-543, Charles City County
Solar + storage
325 MWWithdrawn / abandoned Charles City, VAPJM Sep 2020target 2024
Solar + storage project AG2-070, Charles City County
Solar + storage
325 MWWithdrawn / abandoned Charles City, VAPJM Dec 2020target 2024
Gas project J1838, Dane County
Gas
320 MWWithdrawn / abandoned Dane, WIMISO Jun 2020target 2025
Luzen Solar Energy Center
Solar + storage
313 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2020target 2022
Crossroads Storage
Battery storage
313 MWWithdrawn / abandoned Shasta, CACAISO Apr 2020target 2027
Onshore wind project GEN-2016-114, Mcpherson County
Onshore wind
310 MWWithdrawn / abandoned Mcpherson, KSSPP Oct 20202020
Anacapa
Solar + storage
309 MWWithdrawn / abandoned Santa Barbara, CACAISO Apr 2020target 2023
Solar + storage project J1756, Shelby County
Solar + storage
309 MWWithdrawn / abandoned Shelby, INMISO Jun 2020target 2023

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)