United States βΊ Grid βΊ Interconnection queues βΊ Indiana
SOLAR Β· PJMSolar project AG1-225, Adams County
Solar project AG1-225, Adams County is a 346 MW solar request withdrawn in the PJM interconnection queue, in Adams County, Indiana, connecting to AEP.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2020 (completed)
- Withdrawn / abandonedJun 2024 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AG1-225
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Developer
- ADAMS SOLAR PROJECT, LLC
- Connection point (POI)
- Adams 138 kV
- Location
- Adams County, Indiana
- Technology
- Solar: 346 MW
- Total requested
- 346 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 24 September 2020
- Proposed online date
- December 2023
- Withdrawn
- June 2024
Location
Marker shows the centre of Adams County; the queue data does not give exact sites.
Other requests in Adams County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem