πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Georgia

SOLAR + STORAGE Β· SOUTHEAST

Solar + storage project IC-862, Decatur County

Solar + storage project IC-862, Decatur County is a 400 MW solar + storage request withdrawn in the Southeast interconnection queue, in Decatur County, Georgia, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2020 (completed)
  2. Withdrawn / abandonedJul 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IC-862
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Dothan Road 230 kV Substation
Location
Decatur County, Georgia
Technology
Solar: 400 MW Β· Battery
Total requested
400 MW
Service type
Energy only (ERIS)
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
20 April 2020
Proposed online date
April 2025
Withdrawn
July 2025

Location

Marker shows the centre of Decatur County; the queue data does not give exact sites.

Power plants in Georgia Β· Transmission lines in Georgia

Other requests in Decatur County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem