United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in ERCOT (Texas) (2022 requests) — page 3

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown28556.7 GW
Active in queue56.7 GW285 requests
Agreement signed23.2 GW113 requests
Withdrawn7615.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

285 requests · page 3 of 6
ProjectCapacityStatusLocationRegionQueuedOnline
Owens Solar
Solar · Owens Solar LLC
204 MWPaused / redesign Bosque, TXERCOT Feb 2022target 2025
Glasgow Solar
Solar + storage · Glasgow Solar LLC
204 MWAgreement signed Navarro, TXERCOT Feb 2022target 2027
Timberlakes Solar
Solar · Donegalsol
204 MWIn study Dickens, TXERCOT Nov 2022target 2026
OCI Cobb Creek Solar
Solar + storage · Hillsboro Solar Project LLC
203 MWAgreement signed Hill, TXERCOT Nov 2022target 2027
Sunlight Solar
Solar
203 MWPaused / redesign Ector, TXERCOT Jun 2022target 2027
Alexandrite Storage
Battery storage · Johnson Energy Storage, LLC
203 MWIn study Cameron, TXERCOT Jun 2022target 2026
Wolf Spring Storage
Solar + storage · Wolf Spring Solar, LLC
203 MWAgreement signed Dickens, TXERCOT Dec 2022target 2028
Legato BESS
Battery storage · Legato Storage, LLC
203 MWIn study Wise, TXERCOT Sep 2022target 2028
Fortissimo BESS
Battery storage · Fortissimo BESS, LCC
203 MWIn study Montague, TXERCOT Oct 2022target 2028
Fiji Solar
Solar
203 MWPaused / redesign Limestone, TXERCOT Sep 2022
McMEXICO STORAGE
Battery storage · FRESH AIR ENERGY II, LLC
202 MWIn study Hidalgo, TXERCOT Feb 2022target 2028
Hacienda Storage
Battery storage · Galveston Energy Storage LLC
202 MWIn study Galveston, TXERCOT May 2022target 2026
Staccato BESS
Battery storage · Staccato Storage, LLC
202 MWIn study Fayette, TXERCOT Nov 2022target 2026
Mitchell Plant Road Storage
Battery storage
202 MWPaused / redesign Pecos, TXERCOT Feb 2022
Goldeneye BESS
Battery storage · Black Mountain Energy Storage II
202 MWAgreement signed Bell, TXERCOT Jun 2022target 2028
OCI Cobb Creek ESS
Solar + storage · Hillsboro Solar Project LLC
202 MWAgreement signed Hill, TXERCOT Dec 2022target 2027
Mitchell Plant Road Solar
Solar
202 MWPaused / redesign Pecos, TXERCOT Feb 2022target 2025
Padrino Solar
Solar · Hill Solar II, LLC
201 MWAgreement signed Hill, TXERCOT Sep 2022target 2026
Eldora BESS
Solar + storage · Eldora Energy LLC
201 MWAgreement signed Matagorda, TXERCOT Jun 2022target 2028
Nockenut Springs Solar 4
Solar · Pecan Springs Energy, LLC
201 MWIn study Gonzales, TXERCOT Sep 2022target 2029
Apache Hill BESS
Battery storage · APACHE HILL ENERGY CENTER
201 MWAgreement signed Hood, TXERCOT Nov 2022target 2026
Seragio BESS
Battery storage · Seragio BESS, LLC
201 MWIn study Ector, TXERCOT Sep 2022target 2027
Jasper BESS
Battery storage · Jasper BESS, LLC
201 MWIn study Midland, TXERCOT Sep 2022target 2028
Blue Heron BESS
Battery storage · Blue Heron BESS, LLC
201 MWIn study Reeves, TXERCOT Oct 2022target 2028
Champaign BESS
Battery storage · Champaign BESS, LLC
201 MWAgreement signed Glasscock, TXERCOT Sep 2022target 2027
Moonlight Sonata BESS
Battery storage · Samsung Solar Energy 2, LLC
201 MWIn study Colorado, TXERCOT Sep 2022target 2028
De Los Santos
Battery storage · BRP De Los Santos BESS LLC
201 MWIn study Maverick, TXERCOT May 2022target 2027
Smokey Willie Solar SLF
Solar + storage · Neches Solar, LLC
201 MWIn study Anderson, TXERCOT Jan 2022target 2028
Possum Kingdom BESS
Solar + storage · PK Solar, LLC
201 MWIn study Jack, TXERCOT Sep 2022target 2027
Eldora Solar
Solar + storage · Eldora Energy LLC
201 MWAgreement signed Matagorda, TXERCOT Jun 2022target 2028
Sloan Storage
Battery storage · Sloan Energy Storage LLC
201 MWIn study Henderson, TXERCOT Feb 2022target 2026
APV Plumwood Storage
Battery storage · APV Lonestar Energy LLC
201 MWAgreement signed Chambers, TXERCOT Mar 2022target 2027
Trelas
Battery storage · Trelasol, LLC
201 MWIn study Mcculloch, TXERCOT Sep 2022target 2028
Forts Trail Solar
Solar + storage · JC Central Bluff, LLC
201 MWIn study Taylor, TXERCOT Jun 2022target 2028
HGP Pacesetter BESS
Battery storage
201 MWPaused / redesign Dallas, TXERCOT Sep 2022
Erika Solar
Solar + storage · Erika Solar, LLC
201 MWAgreement signed Kaufman, TXERCOT Jul 2022target 2027
Bar Candela Solar SLF
Solar + storage · Bar Candela Solar Project LLC
200 MWAgreement signed Freestone, TXERCOT Mar 2022target 2027
Triangle Ranch Bravo
Onshore wind · Triangle Ranch Wind
200 MWIn study Cottle, TXERCOT Oct 2022target 2028
Triangle Ranch Charlie
Onshore wind
200 MWPaused / redesign Cottle, TXERCOT Sep 2022target 2025
PSE Chihuahua TX Storage
Battery storage · PureSky Development Inc
200 MWIn study Hidalgo, TXERCOT Dec 2022target 2027
PSE Flores TX Storage
Battery storage · PureSky Development Inc
200 MWIn study Starr, TXERCOT Dec 2022target 2027
Borderland ESC
Battery storage · FRESH AIR ENERGY II, LLC
200 MWIn study Hidalgo, TXERCOT Feb 2022target 2026
Camino Santiago Solar
Solar · Camino Solar Project, LLC
196 MWAgreement signed Milam, TXERCOT Sep 2022target 2027
Wolf Spring Solar
Solar + storage · Wolf Spring Solar, LLC
196 MWAgreement signed Dickens, TXERCOT Dec 2022target 2028
Argenta Storage
Solar + storage · Charter Oak Storage, LLC
192 MWAgreement signed Bee, TXERCOT Jun 2022target 2028
Harryoung Solar
Solar + storage · Gransolar Texas Four LLC
190 MWIn study Cameron, TXERCOT Nov 2022target 2028
Blanket Ranch North Solar
Solar + storage · Blanket Ranch North Solar, LLC
189 MWIn study Brown, TXERCOT Jun 2022target 2028
Maldives Solar (Oncor POI)
Solar
184 MWPaused / redesign Scurry, TXERCOT Dec 2022target 2026
Arroyo Storage
Solar + storage · BT Cantwell Solar, LLC
184 MWAgreement signed Cameron, TXERCOT May 2022target 2026
Leighton Solar SLF
Solar · Lavender Solar LLC
183 MWAgreement signed Limestone, TXERCOT May 2022target 2027

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)