United States › Grid › Interconnection queues › Texas
BATTERY STORAGE · ERCOTTrelas
Trelas is a 201 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Mcculloch County, Texas.
Queue statusIn planning
- PlanningQueued Sep 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget May 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 24INR0416
- Grid region
- ERCOT (Texas)
- Developer
- Trelasol, LLC
- Connection point (POI)
- 76006 Bow Wood 345kV Bus
- Location
- Mcculloch County, Texas
- Technology
- Battery: 201 MW
- Total requested
- 201 MW
- Study phase
- SS Completed, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 2 September 2022
- Proposed online date
- May 2028
Location
Marker shows the centre of Mcculloch County; the queue data does not give exact sites.
Other requests in Mcculloch County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem