United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in CAISO (California) — page 3

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,186619.9 GW
Active in queue188.6 GW429 requests
Agreement signed96.2 GW235 requests
Withdrawn2,186619.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,186 requests · page 3 of 44
ProjectCapacityStatusLocationRegionQueuedOnline
Bellefield Solar 4
Solar + storage
1,017 MWWithdrawn / abandoned Kern, CACAISO Apr 2021target 2025
Leo Wolf Energy Center
Solar + storage
1,017 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2020target 2024
Spotted Horse
Solar + storage
1,016 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Laramide Storage
Battery storage
1,000 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Desert Ruby PV
Solar
1,000 MWWithdrawn / abandoned San Bernardino, CACAISO Jun 2007target 2013
Kern Solar Ranch (Fka California Solar Ranch)
Solar
1,000 MWWithdrawn / abandoned Kern, CACAISO Mar 2011target 2018
Oatfield Hybrid Solar
Solar + storage
1,000 MWWithdrawn / abandoned Kings, CACAISO Apr 2019target 2022
Wildcat Quartszite
Solar
1,000 MWWithdrawn / abandoned Yuma, AZCAISO Jul 2010target 2015
Desert Opal III PV
Solar
1,000 MWWithdrawn / abandoned San Bernardino, CACAISO Jun 2007target 2016
Greyhound Storage
Battery storage
1,000 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Coyote Springs
Solar
960 MWWithdrawn / abandoned Lincoln, NVCAISO Jul 2009target 2015
Jeep Wrangler
Solar
960 MWWithdrawn / abandoned Yuma, AZCAISO Jul 2009target 2014
Menard Energy Storage
Battery storage
950 MWWithdrawn / abandoned Solano, CACAISO Apr 2020target 2023
Sun Streams 5
Solar + storage
948 MWWithdrawn / abandoned Maricopa, AZCAISO Apr 2020target 2025
Ripple Solar
Solar + storage
946 MWWithdrawn / abandoned CACAISO Apr 2023target 2031
La Paz
Solar + storage
943 MWWithdrawn / abandoned Maricopa, AZCAISO Apr 2020target 2024
Eolica De Rumorosa
Onshore wind
941 MWWithdrawn / abandoned Tecate Baja California Mexico, CACAISO Apr 2021target 2035
Huntington Beach
Gas
939 MWWithdrawn / abandoned Orange, CACAISO Apr 2012target 2020
Nathan Creek
Onshore wind
935 MWWithdrawn / abandoned CACAISO Apr 2023target 2030
Jonathan Creek
Onshore wind
935 MWWithdrawn / abandoned CACAISO Apr 2023target 2030
Primrose Hybrid
Solar + storage
912 MWWithdrawn / abandoned Maricopa, AZCAISO Apr 2021target 2025
Center Power
Gas
910 MWWithdrawn / abandoned Los Angeles, CACAISO Apr 2013target 2024
Mira Loma Hybrid Power Project
Gas
910 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2014target 2020
Viejo Hybrid Power
Gas
910 MWWithdrawn / abandoned Riverside, CACAISO Apr 2014target 2019
Harquahala Flats
Solar + storage
900 MWWithdrawn / abandoned Maricopa, AZCAISO May 2017target 2022
Cadiz West
Solar
900 MWWithdrawn / abandoned San Bernardino, CACAISO May 2008target 2015
Encina Generating Project (PH. 1 And 2)
Gas
900 MWWithdrawn / abandoned San Diego, CACAISO Aug 2000target 2008
La Posa
Solar
900 MWWithdrawn / abandoned La Paz, AZCAISO May 2008target 2015
Az Bighorn
Solar
900 MWWithdrawn / abandoned Maricopa, AZCAISO May 2008target 2015
Yuha Desert Battery Storage 2
Battery storage
900 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Ranegras Eagletail
Solar
900 MWWithdrawn / abandoned La Paz, AZCAISO May 2008target 2014
Wonder Solar
Solar + storage
892 MWWithdrawn / abandoned CACAISO Apr 2023target 2029
Three Rocks
Solar + storage
878 MWWithdrawn / abandoned CACAISO Apr 2021target 2024
Cosmos
Battery storage
874 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Magic Valley Wind 2
Wind + storage
871 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
K Road Calico Solar LLC (KRCS) (Fka Calico Solar 1; Ses Solar One)
Solar
850 MWWithdrawn / abandoned San Bernardino, CACAISO May 2005target 2013
Clearwater Solar Generating Station
Solar
840 MWWithdrawn / abandoned Los Angeles, CACAISO Jun 2008target 2014
Blue Star Energy Storage
Battery storage
829 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Brea Linda Energy Storage
Battery storage
829 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Brown Bear Energy Storage
Battery storage
829 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Solar Farm Energy Center
Solar + storage
822 MWWithdrawn / abandoned Tulare, CACAISO Apr 2021target 2026
Hadselville
Solar + storage
816 MWWithdrawn / abandoned Stanislaus, CACAISO Apr 2021target 2025
Estanislau Solar Storage
Solar + storage
816 MWWithdrawn / abandoned San Joaquin, CACAISO Apr 2021target 2024
Yeager Mustang
Solar + storage
815 MWWithdrawn / abandoned Kern, CACAISO Apr 2021target 2027
White Oak Solar
Solar + storage
813 MWWithdrawn / abandoned Nye, NVCAISO Apr 2023target 2029
Yeager Hybrid Solar
Solar + storage
813 MWWithdrawn / abandoned Kern, CACAISO Apr 2019target 2022
Longhorn 1
Solar + storage
812 MWWithdrawn / abandoned Kern, CACAISO Apr 2020target 2024
Ibis
Solar + storage
811 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
WSP 3
Solar
800 MWWithdrawn / abandoned Kings, CACAISO Mar 2011target 2018
Ventura Clean Energy
Gas
778 MWWithdrawn / abandoned Ventura, CACAISO Apr 2013target 2019
Page 3 of 44

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)