🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA — page 267

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 267 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project IC-802, Tattnall County
Solar + storage
85.0 MWWithdrawn / abandoned Tattnall, GASoutheast Aug 2019
Onshore wind project GEN-2023-147, Sioux County
Onshore wind
85.0 MWWithdrawn / abandoned Sioux, NESPP Oct 2023target 2030
Solar + storage project AG2-427, Sussex County
Solar + storage · Old Forty Road Solar, LLC
85.0 MWWithdrawn / abandoned Sussex, VAPJM Feb 2025target 2024
Beck Storage
Battery storage · ACE DevCo NC LLC
85.0 MWWithdrawn / abandoned Chautauqua, NYNYISO Sep 2024
Solar + storage project AC1-206, Greensville County
Solar + storage
85.0 MWWithdrawn / abandoned Greensville, VAPJM Oct 2016target 2019
Onshore wind project U3-012, Mckean County
Onshore wind
85.0 MWWithdrawn / abandoned Mckean, PAPJM Aug 2008target 2011
Onshore wind project G759, Cottonwood County
Onshore wind
84.8 MWWithdrawn / abandoned Cottonwood, MNMISO Jan 2007
Solar project J2442, Ripley County
Solar
84.0 MWWithdrawn / abandoned Ripley, INMISO Sep 2022target 2025
Onshore wind project J3555, Boone County
Onshore wind
84.0 MWWithdrawn / abandoned Boone, IAMISO Apr 2024target 2027
Solar project AG2-118, Clermont County
Solar
84.0 MWWithdrawn / abandoned Clermont, OHPJM Jan 2021target 2024
Battery storage project AH1-481, White County
Battery storage
84.0 MWWithdrawn / abandoned White, INPJM Sep 2021target 2024
Onshore wind project N48, Ogle County
Onshore wind
84.0 MWWithdrawn / abandoned Ogle, ILPJM Jan 2005target 2005
Onshore wind project GEN-2009-060, Washita County
Onshore wind
84.0 MWWithdrawn / abandoned Washita, OKSPP Dec 2009target 2011
Onshore wind project V3-042, Wayne County
Onshore wind
84.0 MWWithdrawn / abandoned Wayne, PAPJM Sep 2009target 2016
Wind
Onshore wind
84.0 MWWithdrawn / abandoned Somerset, MEISO-NE May 2012target 2016
Solar project GEN-2024-SR1, Chouteau County
Solar
84.0 MWWithdrawn / abandoned Chouteau, OKSPP Nov 20232025
Juniper Hybrid
Solar + storage
84.0 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Sonora Solar Generating Station
Solar
84.0 MWWithdrawn / abandoned Imperial, CACAISO Jun 2008target 2011
Bonsall Renewable
Solar + storage
84.0 MWWithdrawn / abandoned San Diego, CACAISO Apr 2015target 2017
Solar project 543, Mcnairy County
Solar
84.0 MWWithdrawn / abandoned Mcnairy, TNSoutheast Apr 2023
Heirloom Renewable
Solar + storage
84.0 MWWithdrawn / abandoned San Diego, CACAISO Apr 2015target 2017
Onshore wind project GI-54, Nodaway County
Onshore wind
84.0 MWWithdrawn / abandoned Nodaway, MOSoutheast May 2016target 2018
Twin Mountain Solar
Solar · Orion Renewable Resources LLC
83.9 MWWithdrawn / abandoned Comanche, TXERCOT Jul 2019target 2023
Solar project IC-653, Mitchell County
Solar
83.9 MWWithdrawn / abandoned Mitchell, GASoutheast Sep 2017
Onshore wind project GEN-2014-009, Bailey County
Onshore wind
83.7 MWWithdrawn / abandoned Bailey, TXSPP Mar 2014target 2016
Battery storage project J3516, Jackson County
Battery storage
83.4 MWWithdrawn / abandoned Jackson, ILMISO Apr 2024target 2026
Sagebrush Solar 1
Solar
83.3 MWWithdrawn / abandoned Kern, CACAISO May 2016target 2020
Solar project J1950, Gibson County
Solar
83.2 MWWithdrawn / abandoned Gibson, INMISO Aug 2021target 2025
Little Falls Solar & BESS
Solar + storage · Hodson Energy Little Falls LLC
83.2 MWWithdrawn / abandoned Herkimer, NYNYISO Feb 2023
Round Hill Solar
Solar
83.0 MWWithdrawn / abandoned Augusta, VAPJM Aug 2018target 2023
Coal project V3-004, Carbon County
Coal
83.0 MWWithdrawn / abandoned Carbon, PAPJM Aug 2009target 2012
Morris Ridge Battery Storage
Battery storage · EDF Renewables Development, Inc.
83.0 MWWithdrawn / abandoned Livingston, NYNYISO Oct 2019
Solar project AG2-222, Rush County
Solar
83.0 MWWithdrawn / abandoned Rush, INPJM Mar 2021target 2024
Solar project 384, Hardeman County
Solar
83.0 MWWithdrawn / abandoned Hardeman, TNSoutheast Jul 2019
Solar project GEN-2022-093, Hempstead County
Solar
83.0 MWWithdrawn / abandoned Hempstead, ARSPP Nov 2022target 2027
Birdie Energy Storage
Battery storage · Birdie Energy Storage, LLC
83.0 MWWithdrawn / abandoned Westchester, NYNYISO Jul 2020
Dusky Storage
Other · Cypress Creek Renewables
83.0 MWWithdrawn / abandoned Hill, TXERCOT Jun 2018target 2020
Other project G257, Gibson County
Other
83.0 MWWithdrawn / abandoned Gibson, INMISO Sep 2002target 2005
Tacoma Power TC-PSE
Gas
83.0 MWWithdrawn / abandoned Skagit, WAWest May 2001target 2002
Solar project IC-575, Mitchell County
Solar
83.0 MWWithdrawn / abandoned Mitchell, GASoutheast Jan 2017
Solar project AE1-130, Bedford County
Solar
83.0 MWWithdrawn / abandoned Bedford, VAPJM Sep 2018target 2020
Springbrooke
Solar · SUNXI LLC
82.8 MWWithdrawn / abandoned Genesee, NYNYISO Aug 2024
Other project AE1-184, Livingston County
Other
82.7 MWWithdrawn / abandoned Livingston, ILPJM Sep 2018target 2022
Sanyo Ave Storage 1
Battery storage
82.6 MWWithdrawn / abandoned San Diego, CACAISO Apr 2020target 2023
Solar project AE2-250, Greensville County
Solar · Wyatt Mill Solar, LLC
82.5 MWWithdrawn / abandoned Greensville, VAPJM Mar 2019target 2021
Solar project GEN-2016-033, Johnston County
Solar
82.3 MWWithdrawn / abandoned Johnston, OKSPP Mar 2016target 2018
Solar project GEN-2016-048, Osage County
Solar
82.3 MWWithdrawn / abandoned Osage, OKSPP Mar 2016target 2019
Gas Turbine
Gas
82.2 MWWithdrawn / abandoned Middlesex, CTISO-NE Jun 2006target 2011
Centre County Wind Facility
Onshore wind
82.0 MWWithdrawn / abandoned Centre, PAPJM Oct 2014target 2019
Val Verde Wind B
Onshore wind · Akuo Energy USA
82.0 MWWithdrawn / abandoned ERCOT Jan 2010target 2015
Page 267 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)