United States βΊ Grid βΊ Interconnection queues βΊ Texas
OTHER Β· ERCOTDusky Storage
Dusky Storage is a 83.0 MW other request withdrawn in the ERCOT interconnection queue, in Hill County, Texas.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2018 (completed)
- Withdrawn / abandonedJan 2019 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 20INR0149
- Grid region
- ERCOT (Texas)
- Developer
- Cypress Creek Renewables
- Connection point (POI)
- tap 138kV 3522 Hillsboro -3546 Lake Whitney
- Location
- Hill County, Texas
- Technology
- Other: 83.0 MW
- Total requested
- 83.0 MW
- Study phase
- FIS
- Queue status
- Withdrawn
- Entered queue
- 28 June 2018
- Proposed online date
- December 2020
- Withdrawn
- January 2019
Location
Marker shows the centre of Hill County; the queue data does not give exact sites.
Other requests in Hill County
- Compadre SolarSolar Β· 406 MW Β· agreement signed
- Blue Skies BESSBattery storage Β· 306 MW Β· agreement signed
- Aquilla Lake 3 WindOnshore wind Β· 297 MW Β· agreement signed
- OCI Cobb Creek SolarSolar + storage Β· 203 MW Β· agreement signed
- OCI Cobb Creek ESSSolar + storage Β· 202 MW Β· agreement signed
- Padrino SolarSolar Β· 201 MW Β· agreement signed
- High Noon SolarSolar + storage Β· 182 MW Β· agreement signed
- Vial BESSBattery storage Β· 135 MW Β· agreement signed
- Three W SolarSolar Β· 111 MW Β· agreement signed
- Midpoint SolarSolar Β· 98.3 MW Β· agreement signed
- High Noon StorageSolar + storage Β· 94.0 MW Β· agreement signed
- Payne BattlecreekSolar Β· 85.0 MW Β· agreement signed
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem