Solar + storage project IC-802, Tattnall County

Solar + storage project IC-802, Tattnall County is a 85.0 MW solar + storage request withdrawn in the Southeast interconnection queue, in Tattnall County, Georgia, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2019 (completed)
  2. Withdrawn / abandonedFeb 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IC-802
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Claxton - Ludowici Primary 115 kV Line
Location
Tattnall County, Georgia
Technology
Solar: 85.0 MW Β· Battery
Total requested
85.0 MW
Service type
NRIS and ERIS
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
23 August 2019
Withdrawn
February 2020

Location

Marker shows the centre of Tattnall County; the queue data does not give exact sites.

Power plants in Georgia Β· Transmission lines in Georgia

Other requests in Tattnall County