SOLAR Β· SOUTHEASTSolar project 25-IC-AV, Tattnall County
Solar project 25-IC-AV, Tattnall County is a 150 MW solar request withdrawn in the Southeast interconnection queue, in Tattnall County, Georgia, connecting to Southern Company.
Queue statusWithdrawn / abandoned
- Planning (completed)
- Withdrawn / abandonedApr 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 25-IC-AV
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Connection point (POI)
- Ohoopee River - Reidsville 115 kV Line
- Location
- Tattnall County, Georgia
- Technology
- Solar: 150 MW
- Total requested
- 150 MW
- Service type
- NRIS and ERIS
- Study phase
- Withdrawn
- Queue status
- Withdrawn
- Withdrawn
- April 2025
Location
Marker shows the centre of Tattnall County; the queue data does not give exact sites.
Other requests in Tattnall County
- SR MendesSolar Β· 60.0 MW Β· under construction
- RV SolarSolar Β· 100 MW Β· in study
- Solar + storage project IC-802, Tattnall CountySolar + storage Β· 85.0 MW Β· withdrawn
- Solar project IC-308, Tattnall CountySolar Β· 80.0 MW Β· withdrawn
- Solar project IC-574, Tattnall CountySolar Β· 80.0 MW Β· withdrawn
- Solar project IC-551, Tattnall CountySolar Β· 52.0 MW Β· withdrawn
- Solar project IC-377, Tattnall CountySolar Β· 50.0 MW Β· withdrawn
- Solar project IC-601, Tattnall CountySolar Β· 40.0 MW Β· withdrawn
- Solar project IC-301, Tattnall CountySolar Β· 20.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem