Solar project IC-601, Tattnall County

Solar project IC-601, Tattnall County is a 40.0 MW solar request withdrawn in the Southeast interconnection queue, in Tattnall County, Georgia, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2017 (completed)
  2. Withdrawn / abandonedJan 2018 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IC-601
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Claxton - Vidalia 115 kV Line, Ohoopee River Tap
Location
Tattnall County, Georgia
Technology
Solar: 40.0 MW
Total requested
40.0 MW
Service type
NRIS and ERIS
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
27 February 2017
Withdrawn
January 2018

Location

Marker shows the centre of Tattnall County; the queue data does not give exact sites.

Power plants in Georgia Β· Transmission lines in Georgia

Other requests in Tattnall County