Solar project IC-308, Tattnall County is a 80.0 MW solar request withdrawn in the Southeast interconnection queue, in Tattnall County, Georgia, connecting to Southern Company.
Queue statusWithdrawn / abandoned
- PlanningQueued Jul 2013 (completed)
- Withdrawn / abandonedJan 2017 (project stopped here)
- ConsentedDec 2015 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- IC-308
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Connection point (POI)
- Statesboro Primary - Vidalia 230 kV Line
- Location
- Tattnall County, Georgia
- Technology
- Solar: 80.0 MW
- Total requested
- 80.0 MW
- Service type
- Energy only (ERIS)
- Study phase
- Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 16 July 2013
- Agreement signed
- 23 December 2015
- Withdrawn
- January 2017
Location
Marker shows the centre of Tattnall County; the queue data does not give exact sites.
Other requests in Tattnall County
- SR MendesSolar Β· 60.0 MW Β· under construction
- RV SolarSolar Β· 100 MW Β· in study
- Solar project 25-IC-AV, Tattnall CountySolar Β· 150 MW Β· withdrawn
- Solar + storage project IC-802, Tattnall CountySolar + storage Β· 85.0 MW Β· withdrawn
- Solar project IC-574, Tattnall CountySolar Β· 80.0 MW Β· withdrawn
- Solar project IC-551, Tattnall CountySolar Β· 52.0 MW Β· withdrawn
- Solar project IC-377, Tattnall CountySolar Β· 50.0 MW Β· withdrawn
- Solar project IC-601, Tattnall CountySolar Β· 40.0 MW Β· withdrawn
- Solar project IC-301, Tattnall CountySolar Β· 20.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem