United States βΊ Grid βΊ Interconnection queues βΊ New York
SOLAR Β· NYISOSpringbrooke
Springbrooke is a 82.8 MW solar request withdrawn in the NYISO interconnection queue, in Genesee County, New York, connecting to NM-NG.
Queue statusWithdrawn / abandoned
- PlanningQueued Aug 2024 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- C24-076
- Grid region
- NYISO (New York)
- Utility / transmission owner
- NM-NG
- Developer
- SUNXI LLC
- Connection point (POI)
- Southeast Batavia-Golah Line 119
- Location
- Genesee County, New York
- Technology
- Solar: 82.8 MW
- Total requested
- 82.8 MW
- Queue status
- Withdrawn
- Entered queue
- 5 August 2024
Location
Marker shows the centre of Genesee County; the queue data does not give exact sites.
Other requests in Genesee County
- Cider SolarSolar Β· 500 MW Β· in study
- Excelsior Energy CenterSolar Β· 280 MW Β· in study
- Brusselville Solar Energy CenterSolar + storage Β· 170 MW Β· in study
- Alabama Solar Park LLCSolar Β· 130 MW Β· in study
- Heritage WindOnshore wind Β· 126 MW Β· in study
- Transit SolarSolar Β· 20.0 MW Β· in study
- Genesee Wind FarmOnshore wind Β· 500 MW Β· withdrawn
- GenWy Wind FarmOnshore wind Β· 479 MW Β· withdrawn
- Genovia StorageBattery storage Β· 300 MW Β· withdrawn
- Genovia StorageBattery storage Β· 300 MW Β· withdrawn
- Genovia StorageBattery storage Β· 300 MW Β· withdrawn
- Sweet Valley SolarSolar Β· 200 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem