🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › New York

SOLAR · NYISO

Transit Solar

Transit Solar is a 20.0 MW solar request in interconnection study in the NYISO interconnection queue, in Genesee County, New York, connecting to NM-NG.

Queue statusIn planning
  1. PlanningQueued Jul 2020 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget May 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
1051
Grid region
NYISO (New York)
Utility / transmission owner
NM-NG
Developer
SED NY Holding LLC
Connection point (POI)
S.E Batavia - Golah 115kV
Location
Genesee County, New York
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Study phase
SIS, FS
Queue status
Active
Entered queue
21 July 2020
Proposed online date
May 2028

Location

Marker shows the centre of Genesee County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Genesee County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem