United States βΊ Grid βΊ Interconnection queues βΊ New York
ONSHORE WIND Β· NYISOGenWy Wind Farm
GenWy Wind Farm is a 479 MW onshore wind request withdrawn in the NYISO interconnection queue, in Genesee County, New York, connecting to NYSEG.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2005 (completed)
- Withdrawn / abandonedMar 2010 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 203
- Grid region
- NYISO (New York)
- Utility / transmission owner
- NYSEG
- Developer
- GenWy Wind, LLC
- Connection point (POI)
- Stolle Rd - Homer City 345kV
- Location
- Genesee County, New York
- Technology
- Wind: 479 MW
- Total requested
- 479 MW
- Queue status
- Withdrawn
- Entered queue
- 21 October 2005
- Withdrawn
- March 2010
Location
Marker shows the centre of Genesee County; the queue data does not give exact sites.
Other requests in Genesee County
- Cider SolarSolar Β· 500 MW Β· in study
- Excelsior Energy CenterSolar Β· 280 MW Β· in study
- Brusselville Solar Energy CenterSolar + storage Β· 170 MW Β· in study
- Alabama Solar Park LLCSolar Β· 130 MW Β· in study
- Heritage WindOnshore wind Β· 126 MW Β· in study
- Transit SolarSolar Β· 20.0 MW Β· in study
- Genesee Wind FarmOnshore wind Β· 500 MW Β· withdrawn
- Genovia StorageBattery storage Β· 300 MW Β· withdrawn
- Genovia StorageBattery storage Β· 300 MW Β· withdrawn
- Genovia StorageBattery storage Β· 300 MW Β· withdrawn
- Sweet Valley SolarSolar Β· 200 MW Β· withdrawn
- Sweet Valley StorageBattery storage Β· 200 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem