GenWy Wind Farm is a 479 MW onshore wind request withdrawn in the NYISO interconnection queue, in Genesee County, New York, connecting to NYSEG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2005 (completed)
  2. Withdrawn / abandonedMar 2010 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
203
Grid region
NYISO (New York)
Utility / transmission owner
NYSEG
Developer
GenWy Wind, LLC
Connection point (POI)
Stolle Rd - Homer City 345kV
Location
Genesee County, New York
Technology
Wind: 479 MW
Total requested
479 MW
Queue status
Withdrawn
Entered queue
21 October 2005
Withdrawn
March 2010

Location

Marker shows the centre of Genesee County; the queue data does not give exact sites.

Power plants in New York Β· Transmission lines in New York

Other requests in Genesee County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem