SOLAR Β· ERCOT

Twin Mountain Solar

Twin Mountain Solar is a 83.9 MW solar request withdrawn in the ERCOT interconnection queue, in Comanche County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2019 (completed)
  2. Withdrawn / abandonedMar 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
21INR0378
Grid region
ERCOT (Texas)
Developer
Orion Renewable Resources LLC
Connection point (POI)
tap 138kV 1649 Hasse - 290 Shilo
Location
Comanche County, Texas
Technology
Solar: 83.9 MW
Total requested
83.9 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
28 July 2019
Proposed online date
December 2023
Withdrawn
March 2022

Location

Marker shows the centre of Comanche County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Comanche County