SOLAR Β· SPP

Solar project GEN-2024-SR1, Chouteau County

Solar project GEN-2024-SR1, Chouteau County is a 84.0 MW solar request withdrawn in the SPP interconnection queue, in Chouteau County, Oklahoma, connecting to GRDA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2023 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. OperatingDec 2025 (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2024-SR1
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
GRDA
Connection point (POI)
345 kV bus of GRDA GREC 1 & 2 Substation
Location
Chouteau County, Oklahoma
Technology
Solar: 84.0 MW
Total requested
84.0 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
29 November 2023
Proposed online date
December 2025
Came online
December 2025

Location

Marker shows the centre of Chouteau County; the queue data does not give exact sites.

Power plants in Oklahoma Β· Transmission lines in Oklahoma

Other requests in Chouteau County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem