Solar project J2442, Ripley County

Solar project J2442, Ripley County is a 84.0 MW solar request withdrawn in the MISO interconnection queue, in Ripley County, Indiana, connecting to DUKE ENERGY INDIANA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2022 (completed)
  2. Withdrawn / abandonedOct 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2442
Grid region
MISO (Midcontinent)
Utility / transmission owner
DUKE ENERGY INDIANA
Connection point (POI)
Batesville 138 kV
Location
Ripley County, Indiana
Technology
Solar: 84.0 MW
Total requested
84.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
15 September 2022
Proposed online date
October 2025
Withdrawn
October 2025

Location

Marker shows the centre of Ripley County; the queue data does not give exact sites.