🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA — page 260

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 260 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J1994, Fond Du Lac County
Solar
97.1 MWWithdrawn / abandoned Fond Du Lac, WIMISO Jul 2021target 2025
Solar project J3260, Lasalle County
Solar
97.0 MWWithdrawn / abandoned Lasalle, ILMISO Mar 2024target 2028
Gas project Q15, Yuma County
Gas
97.0 MWWithdrawn / abandoned Yuma, AZWest Aug 2005target 2007
Solar + storage project GI-CS-2025-13, Weld County
Solar + storage
97.0 MWWithdrawn / abandoned Weld, COWest Sep 2025target 2028
OR-CAL Power
Geothermal · Or-Cal Power, Inc.
97.0 MWWithdrawn / abandoned Deschutes, ORWest Sep 2001target 2003
Agricola Wind
Onshore wind · Liberty Renewables Inc.
97.0 MWWithdrawn / abandoned Cayuga, NYNYISO Aug 2024
combustion turbine
Gas
97.0 MWWithdrawn / abandoned Norfolk, MAISO-NE Mar 2015target 2018
Onshore wind project AC1-227, Botetourt County
Onshore wind
96.6 MWWithdrawn / abandoned Botetourt, VAPJM Oct 2016target 2019
Percy Farm Solar 2
Solar · AELIUS SOLAR CORP
96.6 MWWithdrawn / abandoned ERCOT Jan 2022target 2024
Greenwood Solar II
Solar + storage · North Corners Energy, LLC
96.2 MWWithdrawn / abandoned Perry, PAPJM Sep 2021target 2025
Thalassa Energy Project
Solar
96.0 MWWithdrawn / abandoned Dekalb, INPJM Aug 2019target 2022
EI Oceanside
Onshore wind · Empire Offshore Wind LLC
96.0 MWWithdrawn / abandoned Nassau, NYNYISO Dec 2019
Onshore wind project GI-55, Osage County
Onshore wind
96.0 MWWithdrawn / abandoned Osage, OKSoutheast May 2016target 2018
Onshore wind project G634, Brookings County
Onshore wind
96.0 MWWithdrawn / abandoned Brookings, SDMISO Apr 2006target 2007
Solar + storage project GEN-2023-130, Potter County
Solar + storage
96.0 MWWithdrawn / abandoned Potter, SDSPP Oct 2023target 2027
Other project S66, Erie County
Other
96.0 MWWithdrawn / abandoned Erie, PAPJM Jul 2007target 2009
Onshore wind project J3554, Adair County
Onshore wind
96.0 MWWithdrawn / abandoned Adair, IAMISO Apr 2024target 2027
Hell Gate Energy Storage
Battery storage · NY Power Authority
96.0 MWWithdrawn / abandoned Bronx, NYNYISO Jul 2022
EI Empire ESS I
Battery storage · Empire Offshore Wind LLC
96.0 MWWithdrawn / abandoned Nassau, NYNYISO May 2021
Orangeville Wind
Onshore wind · NY Windpower, LLC
96.0 MWWithdrawn / abandoned Wyoming, NYNYISO Apr 2005
Other project X3-039, Crawford County
Other
96.0 MWWithdrawn / abandoned Crawford, PAPJM Aug 2011target 2014
Solar project J1343, Cerro Gordo County
Solar
96.0 MWWithdrawn / abandoned Cerro Gordo, IAMISO Apr 2019target 2022
Alamo Springs Solar 2
Solar + storage
96.0 MWWithdrawn / abandoned Kern, CACAISO Apr 2015target 2023
Solar project AH1-315, Henry County
Solar
96.0 MWWithdrawn / abandoned Henry, OHPJM Sep 2021target 2025
Gas project GI-0819, Brown County
Gas
96.0 MWWithdrawn / abandoned Brown, SDWest Jul 2008target 2016
Battery storage project GEN-2022-080, Cedar County
Battery storage
96.0 MWWithdrawn / abandoned Cedar, MOSPP Sep 2022target 2027
Beowulf Energy Storage
Battery storage
95.8 MWWithdrawn / abandoned Santa Clara, CACAISO Apr 2021target 2034
Fence Post Solar MW Increase
Solar · Fence Post Solar Project, LLC
95.7 MWWithdrawn / abandoned Navarro, TXERCOT target 2022
Whale Square Energy Storage 2
Battery storage · Astoria Generating Company, L.P.
95.7 MWWithdrawn / abandoned Kings, NYNYISO Sep 2021
South Pier Improvement
Gas · Astoria Generating Co.
95.5 MWWithdrawn / abandoned Kings, NYNYISO May 2012
Battery storage project GI-2021-23, Alamosa County
Battery storage
95.0 MWWithdrawn / abandoned Alamosa, COWest Oct 2021target 2025
Mustang BESS
Battery storage · Viridity Energy Solutions
95.0 MWWithdrawn / abandoned Orange, NYNYISO Sep 2024
Battery Storage
Battery storage
95.0 MWWithdrawn / abandoned Worcester, MAISO-NE Jul 2022target 2023
Solar + storage project Q440, La Paz County
Solar + storage
95.0 MWWithdrawn / abandoned La Paz, AZWest Sep 2021target 2024
Solar project BHCT G25, Pueblo County
Solar
95.0 MWWithdrawn / abandoned Pueblo, COWest target 2020
Hydro project 4, Sanders County
Hydro
95.0 MWWithdrawn / abandoned Sanders, MTWest Jul 2007
Solar + storage project AH2-192
Solar + storage
95.0 MWWithdrawn / abandoned WVPJM Mar 2022target 2024
Solar + storage project 527, Haywood County
Solar + storage
95.0 MWWithdrawn / abandoned Haywood, TNSoutheast Dec 2023target 2024
Mercer County Solar Project
Solar
95.0 MWWithdrawn / abandoned Mercer, KYPJM Mar 2018target 2023
Onshore wind project W3-054A, Accomack County
Onshore wind
95.0 MWWithdrawn / abandoned Accomack, VAPJM Aug 2010target 2013
Solar + storage project AH2-209, Kanawha County
Solar + storage
95.0 MWWithdrawn / abandoned Kanawha, WVPJM Mar 2022target 2024
Solar project J2420, Faribault County
Solar
95.0 MWWithdrawn / abandoned Faribault, MNMISO Sep 2022target 2027
Battery storage project IC-1216, Haralson County
Battery storage
95.0 MWWithdrawn / abandoned Haralson, GASoutheast Dec 2023
Solar + storage project AH2-191
Solar + storage
95.0 MWWithdrawn / abandoned WVPJM Mar 2022target 2024
Solar project AG2-168, Russell County
Solar
95.0 MWWithdrawn / abandoned Russell, VAPJM Feb 2021target 2022
Hidalgo Chillers
Gas · Calpine
95.0 MWWithdrawn / abandoned ERCOT Nov 2012target 2016
Solar + storage project C3-111, Caribou County
Solar + storage
95.0 MWWithdrawn / abandoned Caribou, IDWest May 2023target 2027
Solar project J2025, St. James Parish County
Solar
95.0 MWWithdrawn / abandoned St. James Parish, LAMISO Aug 2021target 2025
Solar project J3714, Scott County
Solar
95.0 MWWithdrawn / abandoned Scott, MSMISO Apr 2024target 2028
Solar project GEN-2022-218, Sharp County
Solar
95.0 MWWithdrawn / abandoned Sharp, ARSPP Mar 2023target 2028
Page 260 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)