South Pier Improvement

South Pier Improvement is a 95.5 MW gas request withdrawn in the NYISO interconnection queue, in Kings County, New York, connecting to ConEd.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2012 (completed)
  2. Withdrawn / abandonedMar 2018 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
382
Grid region
NYISO (New York)
Utility / transmission owner
ConEd
Developer
Astoria Generating Co.
Connection point (POI)
Gowanus Substation 138kV
Location
Kings County, New York
Technology
Gas: 95.5 MW
Total requested
95.5 MW
Queue status
Withdrawn
Entered queue
30 May 2012
Withdrawn
March 2018

Location

Marker shows the centre of Kings County; the queue data does not give exact sites.

Power plants in New York Β· Transmission lines in New York

Other requests in Kings County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem