BATTERY STORAGE · NYISO

Gowanus Energy Storage

Gowanus Energy Storage is a 150 MW battery storage request in interconnection study in the NYISO interconnection queue, in Kings County, New York, connecting to ConEd.

Queue statusIn planning
  1. PlanningQueued Sep 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
C24-178
Grid region
NYISO (New York)
Utility / transmission owner
ConEd
Developer
Astoria Generating Company, L.P.
Connection point (POI)
Gowanus 138kV Substation
Location
Kings County, New York
Technology
Battery: 150 MW
Total requested
150 MW
Queue status
Active
Entered queue
17 September 2024
Proposed online date
June 2028

Location

Marker shows the centre of Kings County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Kings County