United States βΊ Grid βΊ Interconnection queues βΊ Massachusetts
GAS Β· ISO-NEcombustion turbine
combustion turbine is a 97.0 MW gas request withdrawn in the ISO-NE interconnection queue, in Norfolk County, Massachusetts.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2015 (completed)
- Withdrawn / abandonedApr 2016 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 542
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- NSTAR 115kV Edgar substation
- Location
- Norfolk County, Massachusetts
- Technology
- Gas: 97.0 MW Β· Oil
- Total requested
- 97.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 2 March 2015
- Proposed online date
- February 2018
- Withdrawn
- April 2016
Location
Marker shows the centre of Norfolk County; the queue data does not give exact sites.
Power plants in Massachusetts Β· Transmission lines in Massachusetts
Other requests in Norfolk County
- Medway Grid Battery StorageBattery storage Β· 250 MW Β· agreement signed
- Energy StorageBattery storage Β· 170 MW Β· agreement signed
- NEA Bell. Uprate (Northeast Energy Associates, LP)Gas Β· 1.4 MW Β· agreement signed
- Battery StorageBattery storage Β· 300 MW Β· in study
- Medway Peaker - SEMARIGas Β· 208 MW Β· built
- Thomas A. Watson Generating StationGas Β· 108 MW Β· built
- Kearsarge Solar with batterySolar + storage Β· 5.4 MW Β· built
- Battery Storage Increase (QP1238)Battery storage Β· 301 MW Β· withdrawn
- Battery StorageBattery storage Β· 270 MW Β· withdrawn
- Battery StorageBattery storage Β· 254 MW Β· withdrawn
- Battery StorageBattery storage Β· 250 MW Β· withdrawn
- Gas TurbineGas Β· 208 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem