OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA — page 256

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 256 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
EA100W Project
Onshore wind
100 MWWithdrawn / abandoned Chaves, NMWest Mar 2019target 2021
Battery storage project GEN-2024-354, Roosevelt County
Battery storage
100 MWWithdrawn / abandoned Roosevelt, NMSPP Mar 2025target 2030
Solar project J669, Portage County
Solar
100 MWWithdrawn / abandoned Portage, WIMISO Jul 2016target 2018
Solar project LGE-GIS-2019-008, Caldwell County
Solar
100 MWWithdrawn / abandoned Caldwell, KYSoutheast Mar 2019target 2021
Battery storage project Company QW, Washoe County
Battery storage
100 MWWithdrawn / abandoned Washoe, NVWest Mar 2024target 2026
Solar project GEN-2017-186, Cass County
Solar
100 MWWithdrawn / abandoned Cass, MOSPP Nov 2017target 2020
Fort Edward Solar Farm (NY53)
Solar · Fort Edward Solar
100 MWWithdrawn / abandoned Washington, NYNYISO Feb 2023
Richardson BESS
Battery storage · ACE DevCo NC, LLC
100 MWWithdrawn / abandoned St. Lawrence, NYNYISO Sep 2024
Solar + storage project J2771, Coahoma County
Solar + storage
100 MWWithdrawn / abandoned Coahoma, MSMISO Sep 2022target 2027
Onshore wind project H006, Douglas County
Onshore wind
100 MWWithdrawn / abandoned Douglas, ILMISO Apr 2008target 2012
Solar project J605, Morehouse Parish County
Solar
100 MWWithdrawn / abandoned Morehouse Parish, LAMISO May 2016target 2018
PV-46
Solar
100 MWWithdrawn / abandoned Kern, CACAISO Apr 2008target 2011
Onshore wind project 221-E, Uinta County
Onshore wind
100 MWWithdrawn / abandoned Uinta, WYWest May 2008target 2012
Solar + storage project C2-124, Millard County
Solar + storage
100 MWWithdrawn / abandoned Millard, UTWest May 2022target 2025
Solar project J2209, Scott County
Solar
100 MWWithdrawn / abandoned Scott, MOMISO Dec 2021target 2025
Battery storage project 957261, Newberry County
Battery storage
100 MWWithdrawn / abandoned Newberry, SCSoutheast Jun 2024
Solar + storage project C3-058, Carbon County
Solar + storage
100 MWWithdrawn / abandoned Carbon, UTWest May 2023target 2026
Solar project Q180, San Juan County
Solar
100 MWWithdrawn / abandoned San Juan, NMWest Jan 2011target 2015
Solar + storage project 432, Lauderdale County
Solar + storage
100 MWWithdrawn / abandoned Lauderdale, ALSoutheast May 2020
Royerton Solar and Storage
Solar · Royerton Solar, LLC
100 MWWithdrawn / abandoned Delaware, INPJM Mar 2020target 2023
Battery storage project J1639, Lenawee County
Battery storage
100 MWWithdrawn / abandoned Lenawee, MIMISO Jun 2020target 2022
Solar + storage project C3-127, Kane County
Solar + storage
100 MWWithdrawn / abandoned Kane, UTWest May 2023target 2027
Onshore wind project J014, Stearns County
Onshore wind
100 MWWithdrawn / abandoned Stearns, MNMISO Jan 2009target 2010
Solar project J1568, Renville County
Solar
100 MWWithdrawn / abandoned Renville, MNMISO Jun 2020target 2023
Onshore wind project GEN-2007-010N04, Lincoln County
Onshore wind
100 MWWithdrawn / abandoned Lincoln, NESPP Mar 2007
Solar project AF1-246, Charlotte County
Solar
100 MWWithdrawn / abandoned Charlotte, VAPJM Sep 2019target 2022
Solar + storage project AH2-331, Van Wert County
Solar + storage
100 MWWithdrawn / abandoned Van Wert, OHPJM Mar 2022target 2027
Battery storage project GI-2025-11, Mesa County
Battery storage
100 MWWithdrawn / abandoned Mesa, COWest Apr 2025target 2028
Solar project 77, Dorchester County
Solar
100 MWWithdrawn / abandoned Dorchester, SCSoutheast Jan 2018target 2019
Solar + storage project AG2-354, Mingo County
Solar + storage · Mountaineer Solar LLC
100 MWWithdrawn / abandoned Mingo, WVPJM Mar 2021target 2024
Solar project J547, Sherburne County
Solar
100 MWWithdrawn / abandoned Sherburne, MNMISO Mar 2016target 2018
Solar project 50, Georgetown County
Solar
100 MWWithdrawn / abandoned Georgetown, SCSoutheast Nov 2017target 2019
RE Maplewood 2d Solar
Solar · Recurrent Energy
100 MWWithdrawn / abandoned Pecos, TXERCOT Oct 2014target 2020
Gas project GI-1304, Mckenzie County
Gas
100 MWWithdrawn / abandoned Mckenzie, NDWest Apr 2013target 2016
Onshore wind project AC2-155, Pendleton County
Onshore wind
100 MWWithdrawn / abandoned Pendleton, WVPJM Mar 2017target 2019
Solar + storage project 1024, Cache County
Solar + storage
100 MWWithdrawn / abandoned Cache, UTWest May 2018target 2020
Verona Storage
Battery storage · Invenergy Solar Development LLC
100 MWWithdrawn / abandoned Oneida, NYNYISO Nov 2019
Solar project 603, Payette County
Solar
100 MWWithdrawn / abandoned Payette, IDWest May 2021
Mustang County Solar Project
Solar
100 MWWithdrawn / abandoned Pickaway, OHPJM Mar 2019target 2028
Flat Creek Solar II
Solar · Flat Creek Solar NY LLC
100 MWWithdrawn / abandoned Montgomery, NYNYISO Sep 2024
Battery storage project AG2-307, Loudoun County
Battery storage
100 MWWithdrawn / abandoned Loudoun, VAPJM Mar 2021target 2023
Wellhead Power Lathrop
Gas
99.9 MWWithdrawn / abandoned Stanislaus, CACAISO Nov 2004target 2006
Solar project AC2-094, Louisa County
Solar
99.9 MWWithdrawn / abandoned Louisa, VAPJM Mar 2017target 2019
Onshore wind project J814, Clark County
Onshore wind
99.9 MWWithdrawn / abandoned Clark, WIMISO Jun 2017target 2020
Onshore wind project J819, Lafayette County
Onshore wind
99.9 MWWithdrawn / abandoned Lafayette, WIMISO Jun 2017target 2021
Onshore wind project GEN-2008-083, Garza County
Onshore wind
99.9 MWWithdrawn / abandoned Garza, TXSPP Aug 2008target 2010
Onshore wind project J821, Marathon County
Onshore wind
99.9 MWWithdrawn / abandoned Marathon, WIMISO Jun 2017target 2021
Onshore wind project J825, Green County
Onshore wind
99.9 MWWithdrawn / abandoned Green, WIMISO Jun 2017target 2020
Energy Storage
Battery storage
99.9 MWWithdrawn / abandoned Hampden, MAISO-NE Dec 2021target 2024
Onshore wind project J2192, Vermilion County
Onshore wind
99.9 MWWithdrawn / abandoned Vermilion, ILMISO Jun 2022target 2024
Page 256 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)