πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Missouri

SOLAR Β· SPP

Solar project GEN-2017-186, Cass County

Solar project GEN-2017-186, Cass County is a 100 MW solar request withdrawn in the SPP interconnection queue, in Cass County, Missouri, connecting to KCPL.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2017 (completed)
  2. Withdrawn / abandonedSep 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2017-186
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
KCPL
Connection point (POI)
KC South-N. Raymore 161 kV
Location
Cass County, Missouri
Technology
Solar: 100 MW
Total requested
100 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
30 November 2017
Proposed online date
December 2020
Withdrawn
September 2022

Location

Marker shows the centre of Cass County; the queue data does not give exact sites.

Power plants in Missouri Β· Transmission lines in Missouri

Other requests in Cass County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem