United States βΊ Grid βΊ Interconnection queues βΊ Missouri
ONSHORE WIND Β· SPPOnshore wind project GEN-2010-022, Cass County
Onshore wind project GEN-2010-022, Cass County is a 75.0 MW onshore wind request withdrawn in the SPP interconnection queue, in Cass County, Missouri, connecting to MIPU.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2010 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2010-022
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- MIPU
- Connection point (POI)
- Archie 161kV
- Location
- Cass County, Missouri
- Technology
- Wind: 75.0 MW
- Total requested
- 75.0 MW
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 31 March 2010
- Proposed online date
- December 2012
Location
Marker shows the centre of Cass County; the queue data does not give exact sites.
Other requests in Cass County
- Gas project GEN-2020-061, Cass CountyGas Β· 29.0 MW Β· agreement signed
- Battery storage project GEN-2024-170, Cass CountyBattery storage Β· 280 MW Β· in study
- Gas project GEN-2008-129, Cass CountyGas Β· 72.0 MW Β· built
- Battery storage project GEN-2022-164, Cass CountyBattery storage Β· 200 MW Β· withdrawn
- Solar project GEN-2023-087, Cass CountySolar Β· 200 MW Β· withdrawn
- Solar project GEN-2024-275, Cass CountySolar Β· 150 MW Β· withdrawn
- Solar project GEN-2022-213, Cass CountySolar Β· 120 MW Β· withdrawn
- Battery storage project GEN-2024-256, Cass CountyBattery storage Β· 100 MW Β· withdrawn
- Solar project GEN-2017-186, Cass CountySolar Β· 100 MW Β· withdrawn
- Battery storage project GEN-2018-121, Cass CountyBattery storage Β· 50.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem