GAS · SPPGas project GEN-2008-129, Cass County
Gas project GEN-2008-129, Cass County is a 72.0 MW gas request built and operating in the SPP interconnection queue, in Cass County, Missouri, connecting to MIPU.
Request details
- Queue ID
- GEN-2008-129
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- MIPU
- Connection point (POI)
- Pleasant Hill 161kV
- Location
- Cass County, Missouri
- Technology
- Gas: 72.0 MW
- Total requested
- 72.0 MW
- Service type
- Energy only (ERIS)
- Study phase
- IA FULLY EXECUTED/COMMERCIAL OPERATION
- Queue status
- Operational
- Entered queue
- 12 December 2008
- Proposed online date
- February 2002
- Came online
- February 2002
Location
Marker shows the centre of Cass County; the queue data does not give exact sites.
Other requests in Cass County
- Gas project GEN-2020-061, Cass CountyGas · 29.0 MW · agreement signed
- Battery storage project GEN-2024-170, Cass CountyBattery storage · 280 MW · in study
- Battery storage project GEN-2022-164, Cass CountyBattery storage · 200 MW · withdrawn
- Solar project GEN-2023-087, Cass CountySolar · 200 MW · withdrawn
- Solar project GEN-2024-275, Cass CountySolar · 150 MW · withdrawn
- Solar project GEN-2022-213, Cass CountySolar · 120 MW · withdrawn
- Battery storage project GEN-2024-256, Cass CountyBattery storage · 100 MW · withdrawn
- Solar project GEN-2017-186, Cass CountySolar · 100 MW · withdrawn
- Onshore wind project GEN-2010-022, Cass CountyOnshore wind · 75.0 MW · withdrawn
- Battery storage project GEN-2018-121, Cass CountyBattery storage · 50.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem