Solar project J2209, Scott County

Solar project J2209, Scott County is a 100 MW solar request withdrawn in the MISO interconnection queue, in Scott County, Missouri, connecting to AMEREN MISSOURI.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2021 (completed)
  2. Withdrawn / abandonedDec 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2209
Grid region
MISO (Midcontinent)
Utility / transmission owner
AMEREN MISSOURI
Connection point (POI)
Oran 161kV Substation
Location
Scott County, Missouri
Technology
Solar: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
23 December 2021
Proposed online date
September 2025
Withdrawn
December 2025

Location

Marker shows the centre of Scott County; the queue data does not give exact sites.

Power plants in Missouri Β· Transmission lines in Missouri

Other requests in Scott County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem