GAS · CAISOWellhead Power Lathrop
Wellhead Power Lathrop is a 99.9 MW gas request withdrawn in the CAISO interconnection queue, in Stanislaus County, California, connecting to PGAE.
Queue statusWithdrawn / abandoned
- PlanningQueued Nov 2004 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 36
- Grid region
- CAISO (California)
- Utility / transmission owner
- PGAE
- Connection point (POI)
- 115 kV Tesla - Stockton Cogen Trans. Line.
- Location
- Stanislaus County, California
- Technology
- Gas: 99.9 MW
- Total requested
- 99.9 MW
- Study phase
- In Progress
- Queue status
- Withdrawn
- Entered queue
- 1 November 2004
- Proposed online date
- May 2006
Location
Marker shows the centre of Stanislaus County; the queue data does not give exact sites.
Power plants in California · Transmission lines in California
Other requests in Stanislaus County
- Golden FlatsBattery storage · 365 MW · agreement signed
- Oakdale StorageBattery storage · 103 MW · agreement signed
- Crow Creek Solar 1 (Fka: Frontier Solar 1) (Fka As Scatec Westside Solar Ranch I And Stanislaus PV - Phase 1)Solar + storage · 40.0 MW · agreement signed
- AmaneceSolar + storage · 836 MW · in study
- GerasSolar + storage · 268 MW · in study
- Proxima SolarSolar + storage · 352 MW · built
- Central 40Solar · 40.0 MW · built
- Paulsell Solar Energy CenterSolar + storage · 35.0 MW · built
- HadselvilleSolar + storage · 816 MW · withdrawn
- Amanece SolarSolar + storage · 420 MW · withdrawn
- Mountain Valley StorageBattery storage · 306 MW · withdrawn
- Grape Valley StorageBattery storage · 306 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem