United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in CAISO (California) — page 25

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,186619.9 GW
Active in queue188.6 GW429 requests
Agreement signed96.2 GW235 requests
Withdrawn2,186619.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,186 requests · page 25 of 44
ProjectCapacityStatusLocationRegionQueuedOnline
Seahawk Storage 2
Battery storage
150 MWWithdrawn / abandoned CACAISO Apr 2023target 2029
Goal Line
Gas
150 MWWithdrawn / abandoned San Diego, CACAISO May 2008target 2010
Birchwood Energy
Battery storage
150 MWWithdrawn / abandoned CACAISO Apr 2023target 2030
Areva Solar Az I
Solar
150 MWWithdrawn / abandoned Yuma, AZCAISO Mar 2011target 2015
Wildflower Green Energy Farm- Solar
Solar
150 MWWithdrawn / abandoned Los Angeles, CACAISO Mar 2011target 2013
Quartz 1 Solar
Solar
150 MWWithdrawn / abandoned Riverside, CACAISO Apr 2012target 2016
Three Peaks Wind
Onshore wind
150 MWWithdrawn / abandoned Kings, CACAISO Apr 2013target 2016
Kings Solar 4
Solar
150 MWWithdrawn / abandoned Kings, CACAISO Apr 2013target 2016
Angiola Valley Solar Ranch
Solar
150 MWWithdrawn / abandoned Kings, CACAISO Jul 2010target 2016
Monterey Wind
Onshore wind
150 MWWithdrawn / abandoned Monterey, CACAISO Mar 2011target 2013
Tulip Storage
Battery storage
150 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Mule Mountain Solar Project
Solar
150 MWWithdrawn / abandoned Riverside, CACAISO Mar 2011target 2014
Silvertree Greenworks
Solar
150 MWWithdrawn / abandoned Imperial, CACAISO Mar 2011target 2014
Quartz 2 Solar
Solar
150 MWWithdrawn / abandoned Riverside, CACAISO Apr 2012target 2016
Red Mountain Wind Energy Center - C5
Onshore wind
150 MWWithdrawn / abandoned Merced, CACAISO Apr 2012target 2015
Quartzite Solar 7
Solar
150 MWWithdrawn / abandoned Riverside, CACAISO Apr 2014target 2019
Miguel Energy Storage
Battery storage
150 MWWithdrawn / abandoned San Diego, CACAISO Apr 2014target 2016
White Rabbit
Battery storage
150 MWWithdrawn / abandoned Fresno, CACAISO Apr 2021target 2030
Flannelbush
Battery storage
150 MWWithdrawn / abandoned CACAISO Apr 2023target 2029
Red Mountain Ridge
Onshore wind
150 MWWithdrawn / abandoned Kern, CACAISO May 2008target 2012
Antelope Valley Renewable Energy Farm - Wind
Onshore wind
150 MWWithdrawn / abandoned Los Angeles, CACAISO Feb 2010target 2014
Maricopa California Solar Farms I
Solar
150 MWWithdrawn / abandoned Kern, CACAISO Mar 2011target 2015
Sanborn Solar
Solar
150 MWWithdrawn / abandoned Kern, CACAISO Apr 2012target 2015
Mojave Winds
Onshore wind
150 MWWithdrawn / abandoned San Bernardino, CACAISO Jul 2006target 2008
Cuerno Grande Wind
Onshore wind
150 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2021target 2035
Windcharger ESS
Battery storage
150 MWWithdrawn / abandoned Solano, CACAISO Apr 2018target 2021
Manuel Storage
Battery storage
150 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2021target 2025
Maricopa 4 Solar Project
Solar
150 MWWithdrawn / abandoned Kern, CACAISO Apr 2013target 2016
Oro Verde Solar Project (Fka Gateway Solar Energy Project)
Solar
150 MWWithdrawn / abandoned Kern, CACAISO Jul 2009target 2016
Quartz 3 Solar
Solar
150 MWWithdrawn / abandoned Riverside, CACAISO Apr 2013target 2021
Tampadero Solar
Solar
150 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2015target 2021
Pacheco Pass Wind Energy Center
Onshore wind
150 MWWithdrawn / abandoned Fresno, CACAISO Jul 2010target 2014
Iron Mountain Wind Energy
Onshore wind
149 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2007target 2013
Humboldt Energy Facility (Agile Energy)
Gas
147 MWWithdrawn / abandoned Humboldt, CACAISO Apr 2005target 2008
Mojavalon I
Solar
146 MWWithdrawn / abandoned Kern, CACAISO Feb 2010target 2013
S. F. Electric Reliability Generating Plant
Gas
145 MWWithdrawn / abandoned San Francisco, CACAISO Feb 2004target 2008
Arrowhead Junction Solar Project
Solar
145 MWWithdrawn / abandoned San Bernardino, CACAISO May 2008target 2013
Highwind Energy Center
Other
145 MWWithdrawn / abandoned Kern, CACAISO Apr 2019target 2023
Walker Ridge
Onshore wind
145 MWWithdrawn / abandoned Lake, CACAISO May 2016target 2026
Cactus Condor Energy Center
Battery storage
144 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Grindstone Creek Solar
Solar
143 MWWithdrawn / abandoned Tehama, CACAISO Apr 2021target 2031
Kavax Storage
Battery storage
142 MWWithdrawn / abandoned CACAISO Apr 2023target 2030
Desert View Suntower
Solar
141 MWWithdrawn / abandoned Los Angeles, CACAISO Jul 2009target 2017
Fairmont Solar Generating Station
Solar
141 MWWithdrawn / abandoned Los Angeles, CACAISO Jun 2008target 2013
Siberia Phase III Segs
Solar
140 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2012target 2015
Crossroads Wind
Onshore wind
140 MWWithdrawn / abandoned San Bernardino, CACAISO Oct 2006target 2010
Harper Lake Energy Storage
Battery storage
140 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2015target 2021
El Dorado Solar Alternate
Solar
140 MWWithdrawn / abandoned Clark, NVCAISO Jan 2008target 2011
Oso Rojo Golf Course
Solar
140 MWWithdrawn / abandoned Kern, CACAISO Apr 2019target 2021
Timber Hills Wind (Fka Hillcrest Wind Power 1)
Onshore wind
138 MWWithdrawn / abandoned Shasta, CACAISO Feb 2010target 2013
Page 25 of 44

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)