United States › Grid › Interconnection queues › California

SOLAR · CAISO

Fairmont Solar Generating Station

Fairmont Solar Generating Station is a 141 MW solar request withdrawn in the CAISO interconnection queue, in Los Angeles County, California, connecting to SCE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2008 (completed)
  2. Withdrawn / abandonedMar 2011 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
455
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Whirlwind Substation 230 kV
Location
Los Angeles County, California
Technology
Solar: 141 MW
Total requested
141 MW
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
2 June 2008
Proposed online date
October 2013
Withdrawn
March 2011

Location

Marker shows the centre of Los Angeles County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Los Angeles County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem