SOLAR Β· CAISO

El Dorado Solar Alternate

El Dorado Solar Alternate is a 140 MW solar request withdrawn in the CAISO interconnection queue, in Clark County, Nevada, connecting to SCE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2008 (completed)
  2. Withdrawn / abandonedNov 2008 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
298
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
El Dorado 220kV switchyard
Location
Clark County, Nevada
Technology
Solar: 140 MW
Total requested
140 MW
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
23 January 2008
Proposed online date
November 2011
Withdrawn
November 2008

Location

Marker shows the centre of Clark County; the queue data does not give exact sites.

Power plants in Nevada Β· Transmission lines in Nevada

Other requests in Clark County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem