ONSHORE WIND · CAISO

Mojave Winds

Mojave Winds is a 150 MW onshore wind request withdrawn in the CAISO interconnection queue, in San Bernardino County, California, connecting to SCE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2006 (completed)
  2. Withdrawn / abandonedNov 2008 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
114
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Victor 230 kV
Location
San Bernardino County, California
Technology
Wind: 150 MW
Total requested
150 MW
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
12 July 2006
Proposed online date
July 2008
Withdrawn
November 2008

Location

Marker shows the centre of San Bernardino County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in San Bernardino County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem