SOLAR Β· CAISO

Kings Solar 4

Kings Solar 4 is a 150 MW solar request withdrawn in the CAISO interconnection queue, in Kings County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2013 (completed)
  2. Withdrawn / abandonedJul 2013 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
995
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Gates-Midway 230kV line
Location
Kings County, California
Technology
Solar: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
30 April 2013
Proposed online date
June 2016
Withdrawn
July 2013

Location

Marker shows the centre of Kings County; the queue data does not give exact sites.

Power plants in California Β· Transmission lines in California

Other requests in Kings County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem