United States βΊ Grid βΊ Interconnection queues βΊ California
BATTERY STORAGE Β· CAISOSeahawk Storage 2
Seahawk Storage 2 is a 150 MW battery storage request withdrawn in the CAISO interconnection queue, connecting to PGAE.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2023 (completed)
- Withdrawn / abandonedDec 2024 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 54585
- Grid region
- CAISO (California)
- Utility / transmission owner
- PGAE
- Connection point (POI)
- GREEN VALLEY 115 kV
- Location
- California
- Technology
- Battery: 150 MW
- Total requested
- 150 MW
- Service type
- Network resource (NRIS)
- Study phase
- Caiso Cluster 15 Unvalidated
- Queue status
- Withdrawn
- Entered queue
- 17 April 2023
- Proposed online date
- December 2029
- Withdrawn
- December 2024
Location
Marker shows the centre of County; the queue data does not give exact sites.
Power plants in California Β· Transmission lines in California
Other requests in County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem