Quartz 2 Solar is a 150 MW solar request withdrawn in the CAISO interconnection queue, in Riverside County, California, connecting to SCE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2012 (completed)
  2. Withdrawn / abandonedMay 2013 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
902
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Colorado River sub, 230 kV bus
Location
Riverside County, California
Technology
Solar: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
2 April 2012
Proposed online date
December 2016
Withdrawn
May 2013

Location

Marker shows the centre of Riverside County; the queue data does not give exact sites.