United States › Grid › Interconnection queues › California

ONSHORE WIND · CAISO

Red Mountain Wind Energy Center - C5

Red Mountain Wind Energy Center - C5 is a 150 MW onshore wind request withdrawn in the CAISO interconnection queue, in Merced County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2012 (completed)
  2. Withdrawn / abandonedAug 2012 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
924
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Los Banos-Westly 230 kV Line
Location
Merced County, California
Technology
Wind: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
2 April 2012
Proposed online date
December 2015
Withdrawn
August 2012

Location

Marker shows the centre of Merced County; the queue data does not give exact sites.