United States βΊ Grid βΊ Interconnection queues βΊ California
ONSHORE WIND Β· CAISOWalker Ridge
Walker Ridge is a 145 MW onshore wind request withdrawn in the CAISO interconnection queue, in Lake County, California, connecting to PGAE.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2016 (completed)
- Withdrawn / abandonedSep 2022 (project stopped here)
- ConsentedDec 2018 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 1284
- Grid region
- CAISO (California)
- Utility / transmission owner
- PGAE
- Connection point (POI)
- Cortina-Mendocino and Cortina-Eagle Rock 115kV Lines
- Location
- Lake County, California
- Technology
- Wind: 145 MW
- Total requested
- 145 MW
- Service type
- Network resource (NRIS)
- Study phase
- Executed
- Queue status
- Withdrawn
- Entered queue
- 2 May 2016
- Agreement signed
- 7 December 2018
- Proposed online date
- December 2026
- Withdrawn
- September 2022
Location
Marker shows the centre of Lake County; the queue data does not give exact sites.
Power plants in California Β· Transmission lines in California
Other requests in Lake County
- Bottle Rock PowerOther Β· 56.9 MW Β· agreement signed
- West Ford Flat Energy StorageBattery storage Β· 26.3 MW Β· built
- Bear Canyon Energy StorageBattery storage Β· 13.3 MW Β· built
- Geysers Wind ProjectOnshore wind Β· 201 MW Β· withdrawn
- Walker Ridge Wind Energy ParkOnshore wind Β· 66.2 MW Β· withdrawn
- Binkley Power ProjectGeothermal Β· 50.0 MW Β· withdrawn
- Scenic Energy StorageBattery storage Β· 40.4 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem