ONSHORE WIND · CAISOWalker Ridge Wind Energy Park
Walker Ridge Wind Energy Park is a 66.2 MW onshore wind request withdrawn in the CAISO interconnection queue, in Lake County, California, connecting to PGAE.
Queue statusWithdrawn / abandoned
- PlanningQueued Jul 2007 (completed)
- Withdrawn / abandonedJun 2013 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 250
- Grid region
- CAISO (California)
- Utility / transmission owner
- PGAE
- Connection point (POI)
- Redbud-Cortina 115kV line
- Location
- Lake County, California
- Technology
- Wind: 66.2 MW
- Total requested
- 66.2 MW
- Service type
- Network resource (NRIS)
- Study phase
- System Impact Study
- Queue status
- Withdrawn
- Entered queue
- 30 July 2007
- Proposed online date
- August 2014
- Withdrawn
- June 2013
Location
Marker shows the centre of Lake County; the queue data does not give exact sites.
Power plants in California · Transmission lines in California
Other requests in Lake County
- Bottle Rock PowerOther · 56.9 MW · agreement signed
- West Ford Flat Energy StorageBattery storage · 26.3 MW · built
- Bear Canyon Energy StorageBattery storage · 13.3 MW · built
- Geysers Wind ProjectOnshore wind · 201 MW · withdrawn
- Walker RidgeOnshore wind · 145 MW · withdrawn
- Binkley Power ProjectGeothermal · 50.0 MW · withdrawn
- Scenic Energy StorageBattery storage · 40.4 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem