ONSHORE WIND · CAISOGeysers Wind Project
Geysers Wind Project is a 201 MW onshore wind request withdrawn in the CAISO interconnection queue, in Lake County, California, connecting to PGAE.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2004 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 29
- Grid region
- CAISO (California)
- Utility / transmission owner
- PGAE
- Connection point (POI)
- Collector Sub at Geysers #17 Fulton 230 kV line
- Location
- Lake County, California
- Technology
- Wind: 201 MW
- Total requested
- 201 MW
- Study phase
- In Progress
- Queue status
- Withdrawn
- Entered queue
- 29 March 2004
- Proposed online date
- July 2009
Location
Marker shows the centre of Lake County; the queue data does not give exact sites.
Power plants in California · Transmission lines in California
Other requests in Lake County
- Bottle Rock PowerOther · 56.9 MW · agreement signed
- West Ford Flat Energy StorageBattery storage · 26.3 MW · built
- Bear Canyon Energy StorageBattery storage · 13.3 MW · built
- Walker RidgeOnshore wind · 145 MW · withdrawn
- Walker Ridge Wind Energy ParkOnshore wind · 66.2 MW · withdrawn
- Binkley Power ProjectGeothermal · 50.0 MW · withdrawn
- Scenic Energy StorageBattery storage · 40.4 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem