United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in the USA (2021 requests) โ€” page 24

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,149339.1 GW
Active in queue227.7 GW896 requests
Agreement signed73.3 GW270 requests
Withdrawn2,149339.1 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,149 requests ยท page 24 of 43
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project GEN-2021-SR6, Woodward County
Battery storage
80.0 MWWithdrawn / abandoned Woodward, OKSPP Apr 2021target 2023
Solar project AH1-246, Bedford County
Solar
80.0 MWWithdrawn / abandoned Bedford, PAPJM Sep 2021target 2024
Battery storage project J2009, Arkansas County
Battery storage
80.0 MWWithdrawn / abandoned Arkansas, ARMISO Aug 2021target 2025
Battery storage project AH1-244, Fayette County
Battery storage
80.0 MWWithdrawn / abandoned Fayette, PAPJM Sep 2021target 2024
Solar project BHCT G30, Pueblo County
Solar
80.0 MWWithdrawn / abandoned Pueblo, COWest Aug 2021target 2024
Battery storage project AH1-245, Fayette County
Battery storage
80.0 MWWithdrawn / abandoned Fayette, PAPJM Sep 2021target 2024
Solar + storage project AG2-608, Orange County
Solar + storage
80.0 MWWithdrawn / abandoned Orange, VAPJM Mar 2021target 2023
Solar project AG2-539, Union County
Solar
80.0 MWWithdrawn / abandoned Union, OHPJM Mar 2021target 2025
Solar + storage project AG2-464, Jefferson County
Solar + storage
80.0 MWWithdrawn / abandoned Jefferson, WVPJM Mar 2021target 2025
Battery storage project 415, Yellowstone County
Battery storage
80.0 MWWithdrawn / abandoned Yellowstone, MTWest Sep 2021target 2024
Surplus; Pine River Solar
Other
80.0 MWWithdrawn / abandoned MISO Oct 2021
Solar + storage project IC-939, Covington County
Solar + storage
80.0 MWWithdrawn / abandoned Covington, ALSoutheast Mar 2021
Solar project J2257, Evangeline Parish County
Solar
80.0 MWWithdrawn / abandoned Evangeline Parish, LAMISO Aug 2021target 2024
Solar project 2021-G3
Solar
80.0 MWWithdrawn / abandoned West Jun 2021target 2024
Solar project 169712, Montgomery County
Solar
80.0 MWWithdrawn / abandoned Montgomery, NCSoutheast May 2021
Solar + storage project GEN-2021-082, Lea County
Solar + storage
80.0 MWWithdrawn / abandoned Lea, NMSPP Apr 20212024
Solar project AG2-336, Henry County
Solar ยท Reserve Energy Exploration Company
80.0 MWWithdrawn / abandoned Henry, OHPJM Mar 2021target 2023
Solar project AH1-642, Charles County
Solar
80.0 MWWithdrawn / abandoned Charles, MDPJM Sep 2021target 2023
Solar + storage project IC-940, Covington County
Solar + storage
80.0 MWWithdrawn / abandoned Covington, ALSoutheast Mar 2021
Solar project 171542, Scotland County
Solar
80.0 MWWithdrawn / abandoned Scotland, NCSoutheast May 2021
Solar project AH1-312, Edgecombe County
Solar
80.0 MWWithdrawn / abandoned Edgecombe, NCPJM Sep 2021target 2025
Solar project AH1-656, Lunenburg County
Solar
80.0 MWWithdrawn / abandoned Lunenburg, VAPJM Sep 2021target 2024
Solar + storage project AG2-540, Greensville County
Solar + storage
80.0 MWWithdrawn / abandoned Greensville, VAPJM Mar 2021target 2024
Solar project AH1-456, Spotsylvania County
Solar
80.0 MWWithdrawn / abandoned Spotsylvania, VAPJM Sep 2021target 2024
Solar + storage project AH1-090, Surry County
Solar + storage
80.0 MWWithdrawn / abandoned Surry, VAPJM Jul 2021target 2024
Solar project AG2-259, Fluvanna County
Solar
80.0 MWWithdrawn / abandoned Fluvanna, VAPJM Mar 2021target 2024
Solar project J1997, Beauregard Parish County
Solar
80.0 MWWithdrawn / abandoned Beauregard Parish, LAMISO Aug 2021target 2024
Solar project J2313, Sunflower County
Solar
80.0 MWWithdrawn / abandoned Sunflower, MSMISO Sep 2021target 2023
Solar project IC-1004, Marengo County
Solar
80.0 MWWithdrawn / abandoned Marengo, ALSoutheast Dec 2021
Battery storage project GEN-2021-102, Douglas County
Battery storage
80.0 MWWithdrawn / abandoned Douglas, KSSPP May 20212025
Solar project AG2-463, Potter County
Solar
80.0 MWWithdrawn / abandoned Potter, PAPJM Mar 2021target 2025
Solar project IC-981, Early County
Solar
80.0 MWWithdrawn / abandoned Early, GASoutheast Sep 2021
Solar project AH1-643, St. Mary's County
Solar
80.0 MWWithdrawn / abandoned St. Mary's, MDPJM Sep 2021target 2023
Solar project AG2-468, Halifax County
Solar
80.0 MWWithdrawn / abandoned Halifax, VAPJM Mar 2021target 2025
Solar project 168660, Moore County
Solar
80.0 MWWithdrawn / abandoned Moore, NCSoutheast Apr 2021
Solar project AG2-641, Mecklenburg County
Solar
80.0 MWWithdrawn / abandoned Mecklenburg, VAPJM Mar 2021target 2025
Solar + storage project IC-985, Marengo County
Solar + storage
80.0 MWWithdrawn / abandoned Marengo, ALSoutheast Oct 2021
Battery storage project AH1-568, Buchanan County
Battery storage
80.0 MWWithdrawn / abandoned Buchanan, VAPJM Sep 2021target 2025
Onshore wind project 409, Stillwater County
Onshore wind
80.0 MWWithdrawn / abandoned Stillwater, MTWest Feb 2021target 2023
Solar + storage project AH1-414, Leslie County
Solar + storage
80.0 MWWithdrawn / abandoned Leslie, KYPJM Sep 2021target 2025
Battery storage project AH1-190, Lake County
Battery storage
80.0 MWWithdrawn / abandoned Lake, ILPJM Sep 2021target 2025
Solar project 169716, Bladen County
Solar
80.0 MWWithdrawn / abandoned Bladen, NCSoutheast May 2021
Solar + storage project IC-970, Cherokee County
Solar + storage
80.0 MWWithdrawn / abandoned Cherokee, ALSoutheast Jun 2021
Solar project AH1-167, Caroline County
Solar
80.0 MWWithdrawn / abandoned Caroline, VAPJM Aug 2021target 2026
Solar + storage project 617, Clark County
Solar + storage
80.0 MWWithdrawn / abandoned Clark, IDWest Sep 2021
Solar project G0719, Sherman County
Solar
80.0 MWWithdrawn / abandoned Sherman, ORWest Dec 2021target 2025
Solar project 166, Georgetown County
Solar
79.9 MWWithdrawn / abandoned Georgetown, SCSoutheast Oct 2021
Alpine Storage
Battery storage
79.5 MWWithdrawn / abandoned Los Angeles, CACAISO Apr 2021target 2026
Solar + storage project IC-929, Escambia County
Solar + storage
79.0 MWWithdrawn / abandoned Escambia, ALSoutheast Jan 2021target 2024
Solar + storage project IC-931, Dale County
Solar + storage
79.0 MWWithdrawn / abandoned Dale, ALSoutheast Jan 2021

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)