Alpine Storage

Alpine Storage is a 79.5 MW battery storage request withdrawn in the CAISO interconnection queue, in Los Angeles County, California, connecting to SCE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2021 (completed)
  2. Withdrawn / abandonedDec 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
2073
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Neenach Substation 66 kV
Location
Los Angeles County, California
Technology
Battery: 79.5 MW
Total requested
79.5 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
15 April 2021
Proposed online date
April 2026
Withdrawn
December 2022

Location

Marker shows the centre of Los Angeles County; the queue data does not give exact sites.