πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Montana

ONSHORE WIND Β· WEST

Onshore wind project 409, Stillwater County

Onshore wind project 409, Stillwater County is a 80.0 MW onshore wind request withdrawn in the West interconnection queue, in Stillwater County, Montana, connecting to NorthWestern Energy.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2021 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
409
Grid region
West (non-ISO utilities)
Utility / transmission owner
NorthWestern Energy
Connection point (POI)
100kV at Columbus Rapelje Substation
Location
Stillwater County, Montana
Technology
Wind: 80.0 MW
Total requested
80.0 MW
Service type
Network resource (NRIS)
Study phase
Feasiblity Study
Queue status
Withdrawn
Entered queue
25 February 2021
Proposed online date
June 2023

Location

Marker shows the centre of Stillwater County; the queue data does not give exact sites.

Power plants in Montana Β· Transmission lines in Montana

Other requests in Stillwater County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem