BATTERY STORAGE Β· PJMBattery storage project AH1-568, Buchanan County
Battery storage project AH1-568, Buchanan County is a 80.0 MW battery storage request withdrawn in the PJM interconnection queue, in Buchanan County, Virginia, connecting to AEP.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2021 (completed)
- Withdrawn / abandonedDec 2024 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AH1-568
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Keen Mountain 138 kV
- Location
- Buchanan County, Virginia
- Technology
- Battery: 80.0 MW
- Total requested
- 80.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 10 September 2021
- Proposed online date
- June 2025
- Withdrawn
- December 2024
Location
Marker shows the centre of Buchanan County; the queue data does not give exact sites.
Other requests in Buchanan County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem