SOLAR · PJMSolar project AI2-343, Buchanan County
Solar project AI2-343, Buchanan County is a 15.3 MW solar request in interconnection study in the PJM interconnection queue, in Buchanan County, Virginia, connecting to AEP.
Queue statusIn planning
- PlanningQueued Mar 2023 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2025 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AI2-343
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Hurley 69 kV
- Location
- Buchanan County, Virginia
- Technology
- Solar: 15.3 MW
- Total requested
- 15.3 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Active
- Entered queue
- 2 March 2023
- Proposed online date
- December 2025
Location
Marker shows the centre of Buchanan County; the queue data does not give exact sites.
Other requests in Buchanan County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem