United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA — page 222

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 222 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Trailways Energy Storage
Battery storage
102 MWWithdrawn / abandoned Butte, CACAISO Apr 2020target 2023
Onshore wind project GEN-2009-026, Rush County
Onshore wind
102 MWWithdrawn / abandoned Rush, KSSPP Jul 2009target 2012
Onshore wind project J029, Howard County
Onshore wind
102 MWWithdrawn / abandoned Howard, IAMISO Mar 2009target 2012
Onshore wind project GEN-2009-056, Ford County
Onshore wind
102 MWWithdrawn / abandoned Ford, KSSPP Dec 2009target 2012
Onshore wind project J467, Douglas County
Onshore wind
102 MWWithdrawn / abandoned Douglas, ILMISO Jun 2017target 2017
Solar project GEN-2017-089, Texas County
Solar
102 MWWithdrawn / abandoned Texas, OKSPP May 2017target 2021
Onshore wind project GEN-2009-066, Kiowa County
Onshore wind
102 MWWithdrawn / abandoned Kiowa, OKSPP Dec 2009target 2012
Onshore wind project GEN-2009-035, Grady County
Onshore wind
102 MWWithdrawn / abandoned Grady, OKSPP Aug 2009target 2012
Solar plus Battery
Solar + storage
102 MWWithdrawn / abandoned Cheshire, NHISO-NE Sep 2022target 2027
Mandorla (Formly Kirkwood Legacy Hybrid)
Solar + storage
102 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Onshore wind project 28, Idaho County
Onshore wind
102 MWWithdrawn / abandoned Idaho, IDWest Jun 2010target 2012
Meadows Energy Storage
Battery storage
102 MWWithdrawn / abandoned Placer, CACAISO Apr 2020target 2025
Onshore wind project GEN-2009-050, Coffey County
Onshore wind
102 MWWithdrawn / abandoned Coffey, KSSPP Oct 2009target 2015
Keechi Wind Energy Center 345 kV
Onshore wind · Keechi Wind, LLC
102 MWWithdrawn / abandoned ERCOT Mar 2013target 2014
Onshore wind project GEN-2016-152, Burke County
Onshore wind
102 MWWithdrawn / abandoned Burke, NDSPP Nov 2016target 2019
Perry Creek Solar SLF
Solar · Perry Creek Solar, LLC
102 MWWithdrawn / abandoned ERCOT Dec 2022target 2027
Conejo Solar
Solar
102 MWWithdrawn / abandoned Fresno, CACAISO May 2016target 2020
Onshore wind project GEN-2009-058, Ford County
Onshore wind
102 MWWithdrawn / abandoned Ford, KSSPP Dec 2009target 2014
Black Bear Energy Storage 1
Battery storage
102 MWWithdrawn / abandoned San Luis Obispo, CACAISO Apr 2020target 2023
Onshore wind project GEN-2009-043, Rush County
Onshore wind
102 MWWithdrawn / abandoned Rush, KSSPP Sep 2009target 2013
Battery Storage
Battery storage
102 MWWithdrawn / abandoned Worcester, MAISO-NE May 2023target 2026
Onshore wind project G647, Allegan County
Onshore wind
102 MWWithdrawn / abandoned Allegan, MIMISO Jun 2006target 2008
Black Bear Energy Storage 2
Battery storage
102 MWWithdrawn / abandoned San Luis Obispo, CACAISO Apr 2020target 2023
Taylor Storage
Battery storage
102 MWWithdrawn / abandoned San Diego, CACAISO Apr 2021target 2029
Duck Pilot Storage
Battery storage
102 MWWithdrawn / abandoned San Diego, CACAISO Apr 2020target 2024
Battery storage project Q2407*, Pinal County
Battery storage
102 MWWithdrawn / abandoned Pinal, AZWest Feb 2024target 2026
Coastwood Energy Storage
Battery storage
102 MWWithdrawn / abandoned San Diego, CACAISO Apr 2020target 2023
Solar project J566, Acadia Parish County
Solar
102 MWWithdrawn / abandoned Acadia Parish, LAMISO May 2016target 2019
Viking Energy Storage
Battery storage
102 MWWithdrawn / abandoned San Diego, CACAISO Apr 2020target 2024
Estrada Storage
Battery storage
102 MWWithdrawn / abandoned Kern, CACAISO Apr 2021target 2025
Solar project J565, Concordia Parish County
Solar
102 MWWithdrawn / abandoned Concordia Parish, LAMISO May 2016target 2019
Onshore wind project GEN-2011-013, Murray County
Onshore wind
102 MWWithdrawn / abandoned Murray, OKSPP Mar 2011target 2012
Bay Sunshine Hybrid Solar
Solar + storage
102 MWWithdrawn / abandoned San Joaquin, CACAISO Apr 2019target 2022
White Wing II Energy Storage
Other · White Wing II Energy Storage LLC
102 MWWithdrawn / abandoned San Patricio, TXERCOT Oct 2021target 2025
Solar project J568, Calcasieu Parish County
Solar
102 MWWithdrawn / abandoned Calcasieu Parish, LAMISO May 2016target 2019
White Wing I Energy Storage
Other · White Wing I Energy Storage LLC
102 MWWithdrawn / abandoned San Patricio, TXERCOT Oct 2021target 2025
Aurum Mine
Battery storage
102 MWWithdrawn / abandoned Kern, CACAISO Apr 2021target 2024
Montour Solar One
Solar
102 MWWithdrawn / abandoned Montour, PAPJM Mar 2019target 2026
Oakland Energy Reliability Center
Battery storage
102 MWWithdrawn / abandoned Alameda, CACAISO May 2017target 2019
Fife
Battery storage
102 MWWithdrawn / abandoned Alameda, CACAISO Apr 2021target 2024
Solar project J655, Jackson County
Solar
102 MWWithdrawn / abandoned Jackson, ARMISO Jul 2016target 2019
Solar project J656, Craighead County
Solar
102 MWWithdrawn / abandoned Craighead, ARMISO Jul 2016target 2019
Ocee Creek Solar
Solar · OCI LoneSun LLC
102 MWWithdrawn / abandoned Mclennan, TXERCOT Feb 2021target 2025
Solar project J654, Arkansas County
Solar
102 MWWithdrawn / abandoned Arkansas, ARMISO Jul 2016target 2019
Callisto II Energy Center
Other · Saracen II Energy Storage LLC
102 MWWithdrawn / abandoned Harris, TXERCOT Mar 2021target 2023
King Flat Wind Farm 2
Onshore wind
102 MWWithdrawn / abandoned Yolo, CACAISO May 2017target 2020
Onshore wind project Y1-031, Clarion County
Onshore wind
102 MWWithdrawn / abandoned Clarion, PAPJM Feb 2012target 2013
Kaiser Creek Wind
Onshore wind · Calpine
102 MWWithdrawn / abandoned Callahan, TXERCOT Oct 2016target 2021
Bottom Grass BESS MW Increase
Other · Bottom Grass Solar Project, LLC
101 MWWithdrawn / abandoned Colorado, TXERCOT target 2023
Mammoth Energy Storage
Battery storage
101 MWWithdrawn / abandoned Kern, CACAISO Apr 2018target 2021
Page 222 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)