SOLAR Β· MISO

Solar project J655, Jackson County

Solar project J655, Jackson County is a 102 MW solar request withdrawn in the MISO interconnection queue, in Jackson County, Arkansas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2016 (completed)
  2. Withdrawn / abandonedJul 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J655
Grid region
MISO (Midcontinent)
Connection point (POI)
Unknown
Location
Jackson County, Arkansas
Technology
Solar: 102 MW
Total requested
102 MW
Study phase
Feasibility
Queue status
Withdrawn
Entered queue
6 July 2016
Proposed online date
March 2019
Withdrawn
July 2017

Location

Marker shows the centre of Jackson County; the queue data does not give exact sites.

Power plants in Arkansas Β· Transmission lines in Arkansas

Other requests in Jackson County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem