Withdrawn queue requests in the USA (2019 requests) โ€” page 21

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,473226.5 GW
Active in queue109.2 GW589 requests
Agreement signed64.3 GW347 requests
Withdrawn1,473226.5 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,473 requests ยท page 21 of 30
ProjectCapacityStatusLocationRegionQueuedOnline
Hydro project AE2-159, Fayette County
Hydro
48.0 MWWithdrawn / abandoned Fayette, WVPJM Mar 2019target 2021
Gulf Wind 2 Expansion
Onshore wind ยท Texas GULF WIND 2 LLC
47.9 MWWithdrawn / abandoned Kenedy, TXERCOT Mar 2019target 2020
Solar project TCS-33, Bonneville County
Solar
45.0 MWWithdrawn / abandoned Bonneville, IDWest Jun 2019target 2021
Solar project 1143, Bonneville County
Solar
45.0 MWWithdrawn / abandoned Bonneville, IDWest Jun 2019target 2021
Solar project 2019-G5
Solar
45.0 MWWithdrawn / abandoned West Apr 2019target 2021
Horse Run Solar I
Solar + storage
45.0 MWWithdrawn / abandoned Salem, NJPJM Sep 2019target 2028
Solar project AF1-044, Allegany County
Solar
45.0 MWWithdrawn / abandoned Allegany, MDPJM Jun 2019target 2021
Solar project G0627, Klickitat County
Solar
45.0 MWWithdrawn / abandoned Klickitat, WAWest Jul 2019target 2021
Solar
Solar
45.0 MWWithdrawn / abandoned Coos, NHISO-NE Oct 2019target 2024
Solar project AF1-079, Louisa County
Solar
44.8 MWWithdrawn / abandoned Louisa, VAPJM Aug 2019target 2021
Gloucester Solar I
Solar
44.0 MWWithdrawn / abandoned Gloucester, NJPJM Apr 2019target 2026
Solar project AE2-231, Caroline County
Solar
44.0 MWWithdrawn / abandoned Caroline, VAPJM Mar 2019target 2022
Solar project AE2-039, Gloucester County
Solar
44.0 MWWithdrawn / abandoned Gloucester, NJPJM Jan 2019target 2022
Crockett Solar Project
Solar
44.0 MWWithdrawn / abandoned Talbot, MDPJM Feb 2019target 2026
Solar project AE2-279, Adams County
Solar
44.0 MWWithdrawn / abandoned Adams, PAPJM Mar 2019target 2021
Battery storage project AF1-253, Christian County
Battery storage ยท Rolling Farms Wind Project, LLC
43.2 MWWithdrawn / abandoned Christian, ILPJM Sep 2019target 2022
Solar project J1265, Lagrange County
Solar
43.0 MWWithdrawn / abandoned Lagrange, INMISO Apr 2019target 2022
Battery storage project AF2-023, Salem County
Battery storage
42.5 MWWithdrawn / abandoned Salem, NJPJM Nov 2019target 2021
Solar project AE2-189, Butler County
Solar
42.0 MWWithdrawn / abandoned Butler, PAPJM Mar 2019target 2022
Solar project GEN-2019-022, Lea County
Solar
41.0 MWWithdrawn / abandoned Lea, NMSPP Apr 20192024
Gas project GI-81, Dunklin County
Gas
41.0 MWWithdrawn / abandoned Dunklin, MOSoutheast Mar 2019target 2019
Cane Flats Storage
Other ยท Cane Flats Solar Project, LLC
40.6 MWWithdrawn / abandoned Dimmit, TXERCOT Jul 2019target 2023
Kuiper Energy Storage
Battery storage
40.5 MWWithdrawn / abandoned Sonoma, CACAISO Apr 2019target 2021
West Babylon Storage
Battery storage ยท West Babylon Energy Storage, LLC
40.3 MWWithdrawn / abandoned Suffolk, NYNYISO Dec 2019
Ennis-Tractebel (Config 1) Repower
Gas
40.3 MWWithdrawn / abandoned Ellis, TXERCOT Oct 2019
Solar project 246, Gilchrist County
Solar ยท Masked
40.0 MWWithdrawn / abandoned Gilchrist, FLSoutheast Jan 2019target 2021
Battery storage project GEN-2019-051, Barton County
Battery storage
40.0 MWWithdrawn / abandoned Barton, KSSPP May 2019target 2026
Willow Bay Energy Storage
Battery storage ยท JERA Americas Inc.
40.0 MWWithdrawn / abandoned Richmond, NYNYISO Oct 2019
Offshore Wind Increase
Offshore wind
40.0 MWWithdrawn / abandoned MAISO-NE Mar 2019target 2026
Bluebird Energy Storage
Battery storage ยท esVolta, LP
40.0 MWWithdrawn / abandoned Westchester, NYNYISO Feb 2019
Solar + storage project 1161, Crook County
Solar + storage
40.0 MWWithdrawn / abandoned Crook, ORWest Sep 2019target 2022
Gas project GEN-2019-027, Comanche County
Gas
40.0 MWWithdrawn / abandoned Comanche, OKSPP May 2019target 2023
Battery storage project J1230, Wadena County
Battery storage
40.0 MWWithdrawn / abandoned Wadena, MNMISO Apr 2019target 2023
Solar + storage project 1163, Crook County
Solar + storage
40.0 MWWithdrawn / abandoned Crook, ORWest Sep 2019target 2022
Solar + storage project TCS-10, Lincoln County
Solar + storage
40.0 MWWithdrawn / abandoned Lincoln, WAWest Dec 2019target 2021
Battery storage project J1439, Tunica County
Battery storage
40.0 MWWithdrawn / abandoned Tunica, MSMISO Apr 2019target 2022
Astoria Energy Storage 1
Battery storage ยท NRG Astoria Storage LLC
40.0 MWWithdrawn / abandoned Queens, NYNYISO Apr 2019
Solar + storage project Company JR, Lander County
Solar + storage
40.0 MWWithdrawn / abandoned Lander, NVWest Feb 2019target 2021
Solar project AF1-313, Delaware County
Solar
40.0 MWWithdrawn / abandoned Delaware, INPJM Sep 2019target 2022
Solar project AE2-044, Edgecombe County
Solar
40.0 MWWithdrawn / abandoned Edgecombe, NCPJM Jan 2019target 2019
Battery storage project AE2-188, Culpeper County
Battery storage
40.0 MWWithdrawn / abandoned Culpeper, VAPJM Mar 2019target 2020
Olive Solar
Solar ยท ABEI ENERGY&INFRASTRUCTURE LLC
39.6 MWWithdrawn / abandoned Coke, TXERCOT Apr 2019target 2022
Onshore wind project J1244, Houghton County
Onshore wind
38.4 MWWithdrawn / abandoned Houghton, MIMISO Apr 2019target 2021
Solar project AE2-277, Mercer County
Solar
38.2 MWWithdrawn / abandoned Mercer, PAPJM Mar 2019
Solar + storage project IA-PNM-2019-21, Santa Fe County
Solar + storage
36.0 MWWithdrawn / abandoned Santa Fe, NMWest Apr 2019target 2021
Solar project 1170, San Juan County
Solar
35.0 MWWithdrawn / abandoned San Juan, UTWest Oct 2019target 2023
Solar project J1192, Eaton County
Solar
35.0 MWWithdrawn / abandoned Eaton, MIMISO Mar 2019target 2024
Solar
Solar
35.0 MWWithdrawn / abandoned Oxford, MEISO-NE Aug 2019target 2024
Solar project GEN-2019-020, Williams County
Solar
35.0 MWWithdrawn / abandoned Williams, NDSPP May 2019target 2023
Battery storage project J1250, Clay County
Battery storage
35.0 MWWithdrawn / abandoned Clay, ARMISO Apr 2019target 2022

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)