United States › Grid › Interconnection queues › Texas
GAS · ERCOTEnnis-Tractebel (Config 1) Repower
Ennis-Tractebel (Config 1) Repower is a 40.3 MW gas request withdrawn in the ERCOT interconnection queue, in Ellis County, Texas.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2019 (completed)
- Withdrawn / abandonedSep 2020 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 21INR0448
- Grid region
- ERCOT (Texas)
- Location
- Ellis County, Texas
- Technology
- Gas: 40.3 MW
- Total requested
- 40.3 MW
- Queue status
- Withdrawn
- Entered queue
- 31 October 2019
- Withdrawn
- September 2020
Location
Marker shows the centre of Ellis County; the queue data does not give exact sites.
Other requests in Ellis County
- Oystercatcher SolarSolar · 222 MW · agreement signed
- Cumulus Grid BESSBattery storage · 211 MW · agreement signed
- Sol Marina Energy CenterSolar + storage · 175 MW · agreement signed
- Sol Marina Energy Center BESSSolar + storage · 57.2 MW · agreement signed
- Kickstart Energy Storage VIBattery storage · 1,026 MW · in study
- Kickstart Energy Storage VBattery storage · 999 MW · in study
- Two Step SolarSolar · 405 MW · in study
- Galaxy Solar 2Solar · 302 MW · in study
- Galaxy Storage 2Battery storage · 202 MW · in study
- Galaxy StorageSolar + storage · 155 MW · in study
- Bluebonnet Trail SolarSolar · 151 MW · in study
- Galaxy SolarSolar + storage · 148 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem