πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Arkansas

BATTERY STORAGE Β· MISO

Battery storage project J1250, Clay County

Battery storage project J1250, Clay County is a 35.0 MW battery storage request withdrawn in the MISO interconnection queue, in Clay County, Arkansas, connecting to ENTERGY ARKANSAS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2019 (completed)
  2. Withdrawn / abandonedAug 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J1250
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY ARKANSAS
Connection point (POI)
Datto-Corning North 161 kV line
Location
Clay County, Arkansas
Technology
Battery: 35.0 MW
Total requested
35.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA Complete; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
29 April 2019
Proposed online date
October 2022
Withdrawn
August 2020

Location

Marker shows the centre of Clay County; the queue data does not give exact sites.

Power plants in Arkansas Β· Transmission lines in Arkansas

Other requests in Clay County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem