United States › Grid › Interconnection queues › Texas
ONSHORE WIND · ERCOTGulf Wind 2 Expansion
Gulf Wind 2 Expansion is a 47.9 MW onshore wind request withdrawn in the ERCOT interconnection queue, in Kenedy County, Texas.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2019 (completed)
- Withdrawn / abandonedNov 2019 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 20INR0260
- Grid region
- ERCOT (Texas)
- Developer
- Texas GULF WIND 2 LLC
- Connection point (POI)
- 80071 Zorillo 345kV
- Location
- Kenedy County, Texas
- Technology
- Wind: 47.9 MW
- Total requested
- 47.9 MW
- Study phase
- FIS
- Queue status
- Withdrawn
- Entered queue
- 13 March 2019
- Proposed online date
- June 2020
- Withdrawn
- November 2019
Location
Marker shows the centre of Kenedy County; the queue data does not give exact sites.
Other requests in Kenedy County
- Tall Saddle WindOnshore wind · 523 MW · in study
- Green Ocelot SolarSolar + storage · 357 MW · in study
- Tall Saddle SolarSolar · 252 MW · in study
- Green Ocelot StorageSolar + storage · 179 MW · in study
- Gulf Wind 2Onshore wind · 227 MW · suspended
- Stella 2 WindOnshore wind · 201 MW · suspended
- Stella 1 WindOnshore wind · 201 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem